Financial Report   Printer Friendly  Export to Excel  Export to Word  



 Filters

District
 
Community
Phase
Cycle
Sector
   
Financial Agent
Primary Contributor
   

District
Community
Project
Phase
Cycle
Sector
Start Date
Target End Date
Status
Progress
Financial Agent
Primary Contributor
Primary Contributor $
Disbursed To Date $
Disbursed To Date %
Total Budget $
Abdiaziz Waah Dhagahbur(1-4) communities School construction 4 1 Education 11/08/14 27/11/14 Installment 3/3 disbursed 100% DRC DFID 68,000 68,000 100% 82,950
    Community Action Plan 4 1 CAP 04/02/14 25/03/14 CAP Drafted 100% DRC DFID 0 0   0
    Road rehibilitation 4 2 Infrastructure 07/02/15   Community Self Evaluation 0% DRC DFID_II 0 0   0
    Community Action plan update 4 2 CAP 10/12/14 10/12/14 CAP endorsed 100% DRC DFID_II 0 0   0
  Summary for Community: Waah Dhagahbur(1-4) communities (4 detail records)
  SUM                     68,000 68,000   82,950
  Waah Gaariso(1-4) communities Community Action Plan 4 1 CAP 30/03/14 24/04/14 CAP Drafted 100% Not Defined DFID 0 0   0
    Road Rehabilitation 4 1 Infrastructure 02/09/14 30/11/14 Completion and Acceptance of Work 100% DRC DFID 68,000 68,000 100% 83,900
    Community center 4 2 Not Defined 07/02/15   Community Self Evaluation 0% DRC DFID_II 0 0   0
    Community action plan updated 4 2 Not Defined 01/01/15 17/02/15 CAP endorsed 0% DRC DFID_II 0 0   0
  Summary for Community: Waah Gaariso(1-4) communities (4 detail records)
  SUM                     68,000 68,000   83,900
  Waah Lowya Ade(1-4) communities Community action plan updated 0 0 CAP 01/01/15 18/02/15 CAP updated 0% Not Defined DFID_II 0 0   0
    Road rehabilitation 0 0 Not Defined 07/02/15   Community Self Evaluation 0% Not Defined DFID_II 0 0   0
    MCH 4 1 Health 19/08/14 30/11/14 Installment 3/3 disbursed 100% DRC DFID 68,000 68,000 100% 213,276
    Community Action Plan 4 1 CAP 09/02/14 25/03/14 CAP Drafted 100% DRC DFID 0 0   0
  Summary for Community: Waah Lowya Ade(1-4) communities (4 detail records)
  SUM                     68,000 68,000   213,276
  Waah Neero(1-4) communities Health Center 4 1 Health 11/08/14 30/10/14 Completion and Acceptance of Work 100% DRC DFID 56,000 44,800 80% 67,072
    Community Action Plan 4 1 CAP 09/02/14 25/03/14 CAP Endorsed 100% DRC DFID 0 0   0
    community action plan updated 4 2 Infrastructure 01/01/15 23/02/15 CAP updated 0% Not Defined DFID_II 0 0   0
    School construction 4 2 Education 07/02/15   Community Self Evaluation 0% Not Defined DFID_II 0 0   0
  Summary for Community: Waah Neero(1-4) communities (4 detail records)
  SUM                     56,000 44,800   67,072
Summary for District: Abdiaziz (16 detail records)
SUM                     260,000 248,800   447,199
Abudwak Amaano Social Services Access Grant 3 1 SAG 23/01/11 10/05/11 Instalment 1/1 Disbursed 100% DRC DFID 5,000 5,000 100% 5,000
    Community Centre 3 1 Infrastructure 02/11/10 23/08/11 Community Self Evaluation 100% DRC DFID 15,001 15,000 100% 20,049
    Community Action Plan 3 1 CAP 02/10/10 17/11/10 CAP Endorsed 100% DRC DFID 0 0   0
    Market 3 2 Infrastructure 25/03/11 21/10/12 Community Self Evaluation 100% DRC DFID_II 14,993 14,993 100% 19,573
    Community Action Plan Updated 3 2 CAP 07/02/12 19/02/12 CAP endorsed 100% DRC DFID_II 0 0   0
  Summary for Community: Amaano (5 detail records)
  SUM                     34,994 34,993   44,622
  Bal-howd Social Services Access Grant 3 1 SAG 06/03/11 10/05/11 Submission of SAG financial report 100% DRC DFID 5,000 5,000 100% 5,000
    Construction of School 3 1 Education 26/10/10 30/04/11 Community Self Evaluation 100% DRC DFID 15,000 15,000 100% 20,000
    Community Action Plan 3 1 CAP 26/10/10 17/11/10 CAP Endorsed 100% DRC DFID 0 0   0
    Community Centre 3 2 Infrastructure 26/06/12 26/10/12 Community Self Evaluation 100% DRC DFID_II 15,000 15,000 100% 20,225
    Community Action Plan Updated 3 2 CAP 09/02/12 09/02/12 CAP Endorsed 100% DRC DFID_II 0 0   0
  Summary for Community: Bal-howd (5 detail records)
  SUM                     35,000 35,000   45,225
  Balicade Social Services Access Grant 3 1 SAG 01/12/10 10/05/11 Submission of SAG financial report 100% DRC DFID 5,000 5,000 100% 5,000
    Construction of primary and intermediate school 3 1 Education 18/11/10 31/05/11 Community Self Evaluation 100% DRC DFID 15,000 15,000 100% 19,000
    Community Action Plan Updated 3 2 CAP 29/02/12 01/03/12 CAP Updated 100% DRC DFID_II 0 0   0
    MCH 3 2 Health 24/06/12 13/11/12 Community Self Evaluation 100% DRC DFID_II 15,000 15,000 100% 19,183
  Summary for Community: Balicade (4 detail records)
  SUM                     35,000 35,000   43,183
  Bangeele Social Services Access Grant 3 1 SAG 20/02/11 31/05/11 Submission of SAG financial report 100% DRC DFID 5,000 5,000 100% 5,000
    Construction of Health Post 3 1 Health 26/12/10 22/06/11 Community Self Evaluation 100% DRC DFID 15,001 15,001 100% 19,958
    Community Action Plan 3 1 CAP 31/10/10 17/11/10 CAP Endorsed 100% DRC DFID 0 0   0
    Community Centre 3 2 Infrastructure 29/05/12 20/09/12 Completion and Acceptance of Work 100% DRC DFID_II 15,000 15,000 100% 20,225
    Community Action Plan Updated 3 2 CAP 09/02/12 09/02/12 CAP Endorsed 100% DRC DFID_II 0 0   0
    Borehole Rehabilitation 4 1 Water Supply 18/12/13 11/03/14 Completion and Acceptance of Work 100% DRC EC 12,471 12,471 100% 12,471
  Summary for Community: Bangeele (6 detail records)
  SUM                     47,472 47,472   57,654
  Dhabbad Berket Rehabilitation-A 0 0 Water Supply 08/04/14     0% DRC EC 0 0   0
    Berket Rehabilitation-B 0 0 Water Supply 08/04/14 30/05/14   0% DRC EC 0 0   0
    Community Action Plan 3 1 CAP 26/10/10 17/11/10 CAP Endorsed 100% DRC DFID 0 0   0
    Social Services Access Grant 3 1 SAG 12/12/10 10/05/11 Submission of SAG financial report 100% DRC DFID 5,000 5,000 100% 5,000
    Construction of Health Post 3 1 Health 01/12/10 26/06/11 Community Self Evaluation 100% DRC DFID 15,001 15,001 100% 19,958
    Community Action Plan Updated 3 2 CAP 27/04/12 28/04/12 CAP Updated 100% DRC DFID_II 0 0   20,519
    Electricity Generation 3 2 Infrastructure 04/01/12 04/01/12 Community Self Evaluation 100% DRC DFID_II 14,999 14,999 100% 20,519
  Summary for Community: Dhabbad (7 detail records)
  SUM                     35,000 35,000   65,996
  Galmegag Construction of School 3 1 Education 03/02/11 31/05/11 Community Self Evaluation 100% DRC DFID 15,000 15,000 100% 19,000
    Community Action Plan 3 1 CAP 06/01/11 23/01/11 CAP Endorsed 100% DRC DFID 0 0   0
    Social Services Access Grant 3 1 SAG 03/02/11 31/05/11 Submission of SAG financial report 100% DRC DFID 5,000 5,000 100% 5,000
    Community Action Plan Updated 3 2 CAP 05/05/12 05/05/12 CAP endorsed 100% DRC DFID_II 15,000 0 0% 20,225
    Community Centre 3 2 Infrastructure 01/03/12 06/01/13 Community Self Evaluation 100% DRC DFID_II 15,000 15,000 100% 20,225
  Summary for Community: Galmegag (5 detail records)
  SUM                     49,999 35,000   64,449
  Horsed Social Services Access Grant 3 1 SAG 26/12/10 31/05/11 Submission of SAG financial report 100% DRC DFID 5,000 5,000 100% 5,000
    Community Center 3 1 Infrastructure 19/11/10 10/05/11 Community Self Evaluation 100% DRC DFID 15,001 15,001 100% 21,001
    Community Action Plan 3 1 CAP 19/10/10 17/11/10 CAP Endorsed 100% DRC DFID 0 0   0
    Community Action Plan Updated 3 2 CAP 07/02/12 08/02/12 CAP endorsed 100% DRC DFID_II 0 0   0
    Market 3 2 Infrastructure 24/06/12 11/01/13 Community Self Evaluation 100% DRC DFID_II 14,985 14,986 100% 19,520
  Summary for Community: Horsed (5 detail records)
  SUM                     34,986 34,987   45,521
  Kow-Luulyo Construction of Health Post 3 1 Health 01/11/10 31/05/11 Community Self Evaluation 90% DRC DFID 15,000 15,000 100% 19,000
    Community Action Plan 3 1 CAP 26/12/10 26/12/10 CAP Endorsed 100% DRC DFID 0 0   0
    Social Services Access Grant 3 1 SAG 03/02/11 31/05/11 Submission of SAG financial report 100% DRC DFID 5,000 5,000 100% 5,000
    Community Action Plan Updated 3 2 CAP 05/02/12 06/02/12 CAP endorsed 100% DRC DFID_II 5,225 0 0% 20,225
    Community Centre 3 2 Infrastructure 24/06/12 13/11/12 Community self evaluation 100% DRC DFID_II 15,000 15,000 100% 20,225
  Summary for Community: Kow-Luulyo (5 detail records)
  SUM                     40,225 35,000   64,450
  October Social Services Access Grant 3 1 SAG 21/11/10 31/05/11 Submission of SAG financial report 100% DRC DFID 5,000 5,000 100% 5,000
    Community Center 3 1 Infrastructure 02/10/10 31/05/11 Community Self Evaluation 100% DRC DFID 15,001 15,001 100% 18,971
    Community Action Plan 3 1 CAP 02/10/10 17/11/10 CAP Endorsed 100% DRC DFID 0 0   0
    Market 3 2 Income Generation 21/06/12 13/11/12 Community self evaluation 100% DRC DFID_II 14,948 14,948 100% 19,443
    Community Action Plan Updated 3 2 CAP 05/02/12 06/02/12 CAP updated 100% DRC DFID_II 14,948 0 0% 19,443
  Summary for Community: October (5 detail records)
  SUM                     49,897 34,949   62,857
  Shiilamadow Construction of School 3 1 Education 01/01/11 30/05/11 Community Self Evaluation 100% DRC DFID 15,000 15,000 100% 18,820
    Social Services Access Grant 3 1 SAG 02/02/11 31/05/11 Submission of SAG financial report 100% DRC DFID 5,000 5,000 100% 5,000
    Community Action Plan 3 1 CAP 10/01/11 23/01/11 CAP Endorsed 100% DRC DFID 0 0   0
    Health Post 3 2 Health 24/06/12 13/11/12 Community Self Evaluation 100% DRC DFID_II 15,000 15,000 100% 19,370
    Community Action Plan Updated 3 2 CAP 19/02/12 20/02/12 CAP endorsed 100% DRC DFID_II 15,000 0 0% 19,370
  Summary for Community: Shiilamadow (5 detail records)
  SUM                     50,000 35,000   62,560
  Ubah Flood Mitigation 0 0 Water Supply 08/04/14 30/04/14   0% DRC EC 0 0   0
    Community Action Plan 3 1 CAP 19/10/10 17/11/10 CAP Endorsed 100% DRC DFID 0 0   0
    Social Services Access Grant 3 1 SAG 06/02/11 31/05/11 Submission of SAG financial report 100% DRC DFID 5,000 5,000 100% 5,000
    Community Center 3 1 Infrastructure 02/11/10 31/05/11 Community Self Evaluation 100% DRC DFID 15,001 15,001 100% 21,021
    Health Post 3 2 Health 24/06/12 13/11/12 Community Self Evaluation 100% DRC DFID_II 15,000 15,000 100% 19,695
    Community Action Plan Updated 3 2 CAP 07/02/12 08/02/12 CAP endorsed 100% DRC DFID_II 15,000 0 0% 19,695
  Summary for Community: Ubah (6 detail records)
  SUM                     50,001 35,001   65,411
  Waaberi Social Services Access Grant 3 1 SAG 09/01/11 31/05/11 Submission of SAG financial report 100% DRC DFID 5,000 5,000 100% 5,000
    Community Center 3 1 Infrastructure 02/11/10 31/05/11 Community Self Evaluation 100% DRC DFID 15,001 15,000 100% 19,981
    Community Action Plan 3 1 CAP 02/10/10 17/11/10 CAP Endorsed 100% DRC DFID 0 0   0
    Health Post 3 2 Health 24/06/12 13/11/12 Community Self Evaluation 100% DRC DFID_II 15,000 15,000 100% 20,120
    Community Action Plan Updated 3 2 CAP 30/01/12 31/01/12 CAP updated 100% DRC DFID_II 0 0   0
  Summary for Community: Waaberi (5 detail records)
  SUM                     35,001 35,000   45,101
Summary for District: Abudwak (63 detail records)
SUM                     497,574 432,401   667,029
Ainabo Ainabo Hawl-wadaag Slaughter House 3 1 Infrastructure 12/12/11 05/09/12 Community Self Evaluation 100% DRC DFID_II 14,958 14,958 100% 17,812
    Community Action Plan 3 1 CAP 01/12/11 15/12/11 CAP Endorsed 100% DRC DFID_II 0 0   0
    Community Action Plan Updated 3 2 CAP 02/05/13 25/07/13 CAP endorsed 100% DRC SIDA 0 0   0
    Roof Catchment 3 2 Water Supply 07/11/13 13/03/14 Community Self Evaluation 100% DRC SIDA 14,998 14,998 100% 18,193
    Social Access Grant 3 2 SAG 04/02/14 08/04/14 SAG report 100% DRC SIDA 5,000 5,000 100% 5,000
  Summary for Community: Ainabo Hawl-wadaag (5 detail records)
  SUM                     34,956 34,956   41,005
  Ainabo Horseed Community Action Plan 3 1 CAP 01/12/11 15/12/11 CAP Endorsed 100% DRC DFID_II 0 0   0
    Construction of Wall Barrier 3 1 Education 12/12/11 06/06/12 Completion and Acceptance of Work 100% DRC DFID_II 14,715 14,715 100% 16,592
    Community Action Plan updated 3 2 CAP 08/05/13 25/07/13 CAP updated 100% DRC SIDA 0 0   0
    School Extension 3 2 Education 23/10/13 24/03/14 Community Self Evaluation 100% DRC SIDA 14,999 14,999 100% 18,885
    Social Access Grant 3 2 SAG 04/02/14 08/04/14 SAG report 100% DRC SIDA 5,000 5,000 100% 5,000
  Summary for Community: Ainabo Horseed (5 detail records)
  SUM                     34,714 34,714   40,477
  Ainabo Iftin Community Action Plan 3 1 CAP 15/11/11 30/12/11 CAP drafted 100% DRC DFID_II 0 0   0
    Community Centre 3 1 Infrastructure 30/01/12 16/05/12 Completion and Acceptance of Work 100% DRC DFID_II 14,936 14,936 100% 25,954
    School extention 3 2 Education 07/11/13 08/04/14 Community Self Evaluation 100% DRC SIDA 14,999 14,999 100% 18,885
    Community Action Plan Updated 3 2 CAP 14/05/13 25/07/13 CAP endorsed 100% DRC SIDA 0 0   0
    Social Access Grant 3 2 SAG 04/02/14 08/04/14 SAG report 100% DRC SIDA 5,000 5,000 100% 5,000
  Summary for Community: Ainabo Iftin (5 detail records)
  SUM                     34,935 34,935   49,839
  Ceelal Community Centre 3 1 Infrastructure 30/01/12 13/08/12 Community Self Evaluation 100% DRC DFID_II 14,983 14,983 100% 18,577
    Community Action Plan 3 1 CAP 15/02/12 29/02/12 CAP drafted 100% DRC DFID_II 14,983 14,983 100% 18,577
    Community Action Plan Updated 3 2 CAP 17/06/13 25/07/13 CAP endorsed 100% DRC SIDA 0 0   0
    Road Extension 3 2 Infrastructure 04/03/13 30/12/13 Installment 2/3 disbursed 70% DRC SIDA 14,990 14,990 100% 18,528
    Social Access Grant 3 2 SAG 05/02/14 08/04/14 SAG report 100% DRC SIDA 5,000 5,000 100% 5,000
  Summary for Community: Ceelal (5 detail records)
  SUM                     49,956 49,956   60,681
  Dhanaano Community Action Plan 3 1 CAP 01/02/11 15/03/12 CAP drafted 100% DRC DFID_II 0 0   0
    Community Centre 3 1 Infrastructure 30/01/12 16/09/12 Community Self Evaluation 100% DRC DFID_II 14,983 14,983 100% 18,577
  Summary for Community: Dhanaano (2 detail records)
  SUM                     14,983 14,983   18,577
  Dhudhub Community Action Plan 3 1 CAP 01/02/12 15/02/12 CAP drafted 100% DRC DFID_II 0 0   0
    Classroom construction 3 1 Education 30/01/12 16/09/12 Installment 3/3 Disbursed 100% DRC DFID_II 14,988 13,989 93% 18,814
    Community Center 3 2 Infrastructure 12/10/13 30/04/14 Community Self Evaluation 100% DRC SIDA 14,999 14,999 100% 18,194
    Social Access Grant 3 2 SAG 18/02/14 08/04/14 SAG report 100% DRC SIDA 5,000 5,000 100% 5,000
    Community Action Plan Updated 3 2 CAP 12/06/13 25/07/13 CAP endorsed 100% DRC SIDA 0 0   0
  Summary for Community: Dhudhub (5 detail records)
  SUM                     34,986 33,987   42,007
  Gadhka Community Action Plan 3 1 CAP 15/01/12 30/01/12 CAP endorsed 100% DRC DFID_II 0 0   0
    Community Centre 3 1 Infrastructure 30/01/12 16/08/12 Completion and Acceptance of Work 100% DRC DFID_II 14,983 14,983 100% 18,577
  Summary for Community: Gadhka (2 detail records)
  SUM                     14,983 14,983   18,577
  Gunburo Xaangeeye Classroom construction 3 1 Education 30/01/12 16/08/12 Installment 3/3 Disbursed 100% DRC DFID_II 14,988 14,988 100% 18,814
    Community Action Plan 3 1 CAP 10/11/11 15/03/12 CAP endorsed 100% DRC DFID_II 14,988 14,988 100% 18,814
    Community Action Plan Updated 3 2 CAP 18/06/13 25/07/13 CAP endorsed 100% DRC SIDA 0 0   0
    Construction of 1 roof catchment 3 2 Education 04/05/14 30/06/14 3rd Installment disbursement 80% DRC SIDA 1,392 1,392 100% 1,672
    Rehabilitation of Berkats 3 2 Water Supply 28/11/13 10/04/14 Community Self Evaluation 100% DRC SIDA 13,372 13,372 100% 16,324
    Social Access Grant 3 2 SAG 04/02/14 08/04/14 SAG report 100% DRC SIDA 5,000 5,000 100% 5,000
  Summary for Community: Gunburo Xaangeeye (6 detail records)
  SUM                     49,739 49,739   60,623
  Habari-heshay Community Action Plan 3 1 CAP 15/12/11 30/01/12 CAP endorsed 100% DRC DFID_II 0 0   0
    School construction 3 1 Education 30/01/12 19/06/12 Installment 3/3 Disbursed 100% DRC DFID_II 14,921 14,921 100% 19,447
  Summary for Community: Habari-heshay (2 detail records)
  SUM                     14,921 14,921   19,447
  Higlo Community Action Plan 3 1 CAP 01/01/12 15/03/12 CAP drafted 100% DRC DFID_II 0 0   0
    Community Centre 3 1 Infrastructure 30/01/12 19/06/12 Installment 3/3 Disbursed 100% DRC DFID_II 14,899 14,899 100% 18,493
    Rehabilitation of Wells and Water Diversion 3 2 Water Supply 10/11/13 10/04/14 Community Self Evaluation 100% DRC SIDA 13,313 13,313 100% 16,089
    Social Access Grant 3 2 SAG 04/02/14 08/04/14 SAG report 100% DRC SIDA 511 5,000 978% 511
    Community Action Plan Updated 3 2 CAP 29/04/13 25/07/13 CAP endorsed 100% DRC SIDA 0 0   0
    Construction of shallow well 3 2 Water Supply 14/04/14 08/07/14 Last Installment disbursement 100% DRC SIDA 1,926 1,571 82% 2,281
  Summary for Community: Higlo (6 detail records)
  SUM                     30,650 34,784   37,375
  Oog Community Action Plan 3 1 CAP 15/02/12 29/02/12 CAP Endorsed 100% DRC DFID_II 0 0   0
    School extension 3 1 Education 30/01/12 26/09/12 Community Self Evaluation 100% DRC DFID_II 14,830 14,831 100% 17,785
    Community Center 3 2 Infrastructure 13/10/13 30/12/13 Community Self Evaluation 80% DRC SIDA 14,998 11,999 80% 18,193
    Social Access Grant 3 2 SAG 04/02/14 06/05/14 SAG report 100% DRC SIDA 5,000 5,000 100% 5,000
    Community Action Plan Updated 3 2 CAP 07/07/13 25/07/13 CAP endorsed 100% DRC SIDA 0 0   0
  Summary for Community: Oog (5 detail records)
  SUM                     34,828 31,829   40,978
  Qoridheere Community Action Plan 3 1 CAP 01/01/12 15/03/12 CAP endorsed 100% DRC DFID_II 0 0   0
    Latrine construction 3 1 Sanitation 30/01/12 11/07/12 Community Self Evaluation 100% DRC DFID_II 14,949 14,943 100% 18,909
    Construction of Class Rooms 3 2 Education 03/02/13 30/12/13 Community Self Evaluation 70% DRC SIDA 15,000 15,000 100% 18,886
    Social Access Grantr 3 2 SAG 13/02/14 08/04/14 Submission of SAG financial report 100% DRC SIDA 5,000 5,000 100% 5,000
    Community Action Plan Updated 3 2 CAP 05/11/13 25/07/13 CAP endorsed 100% DRC SIDA 0 0   0
  Summary for Community: Qoridheere (5 detail records)
  SUM                     34,949 34,943   42,795
  Wadaamagoo Community Action Plan 3 1 CAP 15/12/11 30/12/11 CAP drafted 100% DRC DFID_II 0 0   0
    Community Market 3 1 Income Generation 30/01/12 11/07/12 Community Self Evaluation 100% DRC DFID_II 15,063 15,064 100% 19,032
    Social Access Grant 3 2 SAG 04/02/14 06/05/14 SAG report 100% DRC SIDA 5,000 5,000 100% 5,000
    Community Action Plan Updated 3 2 CAP 14/06/13 14/06/13 CAP endorsed 100% DRC SIDA 0 0   0
    Roof Catchment 3 2 Water Supply 01/01/14 10/04/14 Community Self Evaluation 100% DRC SIDA 14,993 14,993 100% 18,630
  Summary for Community: Wadaamagoo (5 detail records)
  SUM                     35,056 35,056   42,662
  War'idaad Community Action Plan 3 1 CAP 01/01/12 15/01/12 CAP endorsed 100% DRC DFID_II 0 0   0
    Community Centre 3 1 Infrastructure 30/01/12 02/10/12 Community Self Evaluation 100% DRC DFID_II 14,918 14,918 100% 18,512
    Construction/Extension class rooms 3 2 Education 06/01/14 10/04/14 Community Self Evaluation 100% DRC SIDA 15,000 15,000 100% 18,886
    Social Access Grant 3 2 SAG 12/02/14 13/04/14 Submission of SAG financial report 100% DRC SIDA 5,000 5,000 100% 5,000
    Community Action Plan Updated 3 2 CAP 09/06/13 25/07/13 CAP endorsed 100% DRC SIDA 0 0   0
  Summary for Community: War'idaad (5 detail records)
  SUM                     34,917 34,917   42,397
  Wiriir Community Centre 3 1 Infrastructure 30/01/12 03/10/12 Community Self Evaluation 100% DRC DFID_II 14,918 14,918 100% 18,512
    Community Action Plan 3 1 CAP 15/01/12 30/01/12 CAP drafted 100% DRC DFID_II 0 0   0
  Summary for Community: Wiriir (2 detail records)
  SUM                     14,918 14,918   18,512
Summary for District: Ainabo (65 detail records)
SUM                     469,490 469,620   575,952
Aw-Bare Awbare CAP 1 1 Not Defined 02/10/14 02/10/14   0% DRC Not Defined 0 0   0
  Summary for Community: Awbare (1 detail records)
  SUM                     0 0   0
  Baldere CAP 1 2 Education 07/11/13     0% DRC DANIDA 0 0   0
    CAP 2 1 Water Supply 06/08/13 06/08/13   0% DRC Not Defined 0 0   0
  Summary for Community: Baldere (2 detail records)
  SUM                     0 0   0
  Dar Wanaje CAP 1 1 Health 01/05/13 31/05/13   0% DRC DANIDA 0 0   0
  Summary for Community: Dar Wanaje (1 detail records)
  SUM                     0 0   0
  Dil'a CAP 1 1 Water Supply 01/07/14 01/07/14   100% DRC Not Defined 0 0   0
  Summary for Community: Dil'a (1 detail records)
  SUM                     0 0   0
  Gedi Toreg CAP 1 1 Education 07/07/14 06/11/14   100% DRC Not Defined 0 0   0
  Summary for Community: Gedi Toreg (1 detail records)
  SUM                     0 0   0
  Gedka Arada CAP 2 1 Education 07/11/13     0% DRC DANIDA 0 0   0
  Summary for Community: Gedka Arada (1 detail records)
  SUM                     0 0   0
  Herosan CAP 1 1 Education 26/04/13 12/07/13   0% DRC DANIDA 0 0   0
  Summary for Community: Herosan (1 detail records)
  SUM                     0 0   0
  Kabri Nuno CAP 1 1 Agriculture Extension 22/04/13 17/09/13   0% DRC DANIDA 0 0   0
  Summary for Community: Kabri Nuno (1 detail records)
  SUM                     0 0   0
  Lafa Isse CAP 1 1 Education 30/11/14 30/11/14   0% DRC Not Defined 0 0   0
  Summary for Community: Lafa Isse (1 detail records)
  SUM                     0 0   0
  Lafta Kidiga CAP 1 1 Education 24/04/13 22/06/13   0% DRC DANIDA 0 0   0
  Summary for Community: Lafta Kidiga (1 detail records)
  SUM                     0 0   0
  Libah Ful CAP 1 1 Water Supply 29/04/13 24/10/13 Procurement activity 0% DRC DANIDA 0 0   0
  Summary for Community: Libah Ful (1 detail records)
  SUM                     0 0   0
  Magalo Buti CAP 1 1 Water Supply 23/04/13 06/05/13   0% DRC DANIDA 0 0   0
  Summary for Community: Magalo Buti (1 detail records)
  SUM                     0 0   0
  Mohammed Ali CAP 1 1 Agriculture Extension 25/04/13 28/10/13   0% DRC Not Defined 0 0   0
  Summary for Community: Mohammed Ali (1 detail records)
  SUM                     0 0   0
  Sheder CAP 1 1 Education 15/08/14 15/08/14   0% DRC Not Defined 0 0   0
  Summary for Community: Sheder (1 detail records)
  SUM                     0 0   0
Summary for District: Aw-Bare (15 detail records)
SUM                     0 0   0
Badhan Buraan Community Action Plan 3 1 CAP 14/05/13 23/06/13 CAP endorsed 100% DRC EC 0 0   0
    Community Market 3 1 Infrastructure 22/10/13 31/12/13 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 18,500
  Summary for Community: Buraan (2 detail records)
  SUM                     15,000 15,000   18,500
  Cawsane Community Action Plan 3 1 Not Defined 14/05/13 24/06/13 CAP endorsed 0% DRC EC 0 0   0
    School extension 3 1 Education 22/10/13 31/12/13 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 18,500
  Summary for Community: Cawsane (2 detail records)
  SUM                     15,000 15,000   18,500
  Curcuro Community Action Plan 3 1 CAP 13/04/13 23/06/13 CAP Drafted 100% DRC EC 0 0   0
    Primary school extention 3 1 Education 22/10/13 31/12/13 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 18,500
  Summary for Community: Curcuro (2 detail records)
  SUM                     15,000 15,000   18,500
  Elbuh Community Action Plan 3 1 CAP 06/05/13 15/06/13 CAP Endorsed 100% DRC EC 0 0   0
    Market 3 1 Infrastructure 14/05/13 03/04/14 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 18,500
  Summary for Community: Elbuh (2 detail records)
  SUM                     15,000 15,000   18,500
  Geeldoora Community Action Plan 3 1 CAP 14/05/13 23/06/13 CAP drafted 100% DRC EC 0 0   0
    Health Post 3 1 Health 14/05/13 03/04/14 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 18,500
  Summary for Community: Geeldoora (2 detail records)
  SUM                     15,000 15,000   18,500
  Golis Community Action Plan 3 1 CAP 14/05/13 23/06/13 CAP endorsed 100% Not Defined EC 0 0   0
    Stadium 3 1 Infrastructure 24/06/13 03/04/14 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 18,500
  Summary for Community: Golis (2 detail records)
  SUM                     15,000 15,000   18,500
  Habaashwacle New school construction 3 1 Education 01/06/13 31/12/13 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 18,500
    Community Action Plan 3 1 CAP 10/04/13 23/06/13 CAP endorsed 100% DRC EC 0 0   0
  Summary for Community: Habaashwacle (2 detail records)
  SUM                     15,000 15,000   18,500
  Habarshiro School Extension 3 1 Education 24/06/13 30/04/14 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 18,500
    Community Action Plan 3 1 CAP 14/05/13 23/06/13 CAP endorsed 100% DRC EC 0 0   0
  Summary for Community: Habarshiro (2 detail records)
  SUM                     15,000 15,000   18,500
  Hadaaftimo Market 3 1 Infrastructure 01/06/13 31/12/13 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 18,500
    Community Action Plan 3 1 CAP 30/04/13 23/06/13 CAP Endorsed 100% DRC EC 0 0   0
  Summary for Community: Hadaaftimo (2 detail records)
  SUM                     15,000 15,000   18,500
  Horseed Community Center 3 1 Infrastructure 01/06/13 31/12/13 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 18,500
    Community Action Plan 3 1 CAP 14/05/13 23/06/13 CAP endorsed 100% DRC EC 0 0   0
  Summary for Community: Horseed (2 detail records)
  SUM                     15,000 15,000   18,500
  Iftin Community Centre 3 1 Infrastructure 01/06/13 31/12/13 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 18,500
    Community Action Plan 3 1 CAP 15/04/13 22/06/13 CAP Drafted 100% DRC EC 0 0   0
  Summary for Community: Iftin (2 detail records)
  SUM                     15,000 15,000   18,500
  Mindigale Community Action Plan 3 1 CAP 15/05/13 24/06/13 CAP endorsed 100% DRC EC 0 0   0
    Health Post 3 1 Health 01/06/13 31/12/13 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 18,500
  Summary for Community: Mindigale (2 detail records)
  SUM                     15,000 15,000   18,500
  Rad Community Center 3 1 Infrastructure 01/06/13 31/12/13 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 19,800
    Community Action Plan 3 1 CAP 15/05/13 23/06/13 CAP endorsed 100% DRC EC 0 0   0
  Summary for Community: Rad (2 detail records)
  SUM                     15,000 15,000   19,800
  Waberi Community Action Plan 3 1 CAP 30/10/13 31/12/13 CAP Drafted 100% DRC EC 0 0   0
    New School Construction 3 1 Education 01/06/13 31/12/13 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 18,500
  Summary for Community: Waberi (2 detail records)
  SUM                     15,000 15,000   18,500
  Wadajir Community Action Plan 3 1 CAP 14/05/13 14/06/13 CAP Drafted 100% DRC EC 0 0   0
    Community Centre 3 1 Infrastructure 01/06/13 31/12/13 Completion and Acceptance of Work 100% DRC EC 15,000 15,000 100% 18,500
  Summary for Community: Wadajir (2 detail records)
  SUM                     15,000 15,000   18,500
Summary for District: Badhan (30 detail records)
SUM                     225,000 225,000   278,800
Beletweyne Bacaad Social Access Grant 2 1 SAG 15/12/09 27/09/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Social Services Access Grant(additional funding) 2 1 SAG 26/04/11   Instalment 1/1 Disbursed 100% DRC WB 5,900 5,900 100% 5,900
    commmunity action plan 2 1 CAP 03/12/09 30/03/10 CAP updated 100% DRC WB 0 0   0
    Construction of Irrigation System 2 1 Agriculture Extension 31/12/09 09/11/10 Completion and Acceptance of work 100% DRC WB 14,672 14,673 100% 20,480
    Community Action Plan Updated 3 2 CAP 01/01/13 30/06/13 CAP endorsed 100% DRC DFID 0 0   0
    Agriculture (Rehabilitation of old Canal 3 2 Water Supply 06/04/13 24/04/14 Community Self Evaluation 100% DRC DFID 15,000 15,000 100% 18,150
  Summary for Community: Bacaad (6 detail records)
  SUM                     40,572 40,573   49,530
  Beerxaano Socail Access Grant 2 1 SAG 15/12/09 31/07/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Action Plan 2 1 CAP 03/12/09 08/03/10 CAP updated 100% DRC WB 0 0   0
    Construction of Marketplace 2 1 Infrastructure 31/12/09 09/11/10 Completion and Acceptance of work 100% DRC WB 14,603 14,603 100% 18,403
  Summary for Community: Beerxaano (3 detail records)
  SUM                     19,603 19,603   23,403
  Caagsibiri community action plan 2 1 CAP 03/12/09 23/03/10 CAP Endorsed 100% DRC WB 0 0   0
    Construction of School 2 1 Education 31/12/09 25/11/10 Completion and Acceptance of work 100% DRC WB 14,673 14,673 100% 18,773
    Social Access Grant 2 1 SAG 15/12/09 03/09/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
  Summary for Community: Caagsibiri (3 detail records)
  SUM                     19,673 19,673   23,773
  Caloolacad Community Action Plan 2 1 CAP 03/12/09 28/02/10 CAP Endorsed 100% DRC WB 0 0   0
    Construction of Irrigation System 2 1 Agriculture Extension 31/12/09 09/11/10 Completion and Acceptance of work 100% DRC WB 14,214 14,214 100% 19,363
    Social Access Grant 2 1 SAG 15/12/09 31/07/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
  Summary for Community: Caloolacad (3 detail records)
  SUM                     19,214 19,214   24,363
  Camaloow Community Action Plan 2 1 CAP 03/12/09 28/02/10 CAP Endorsed 100% DRC WB 0 0   0
    Social Access Grant 2 1 SAG 15/12/09 31/07/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Construction of Irrigation System 2 1 Agriculture Extension 31/12/09 09/11/10 Completion and Acceptance of work 100% DRC WB 14,187 14,187 100% 18,283
  Summary for Community: Camaloow (3 detail records)
  SUM                     19,187 19,187   23,283
  Dharkeynta Community action plan 2 1 CAP 03/12/09 11/07/10 CAP Endorsed 100% DRC WB 0 0   0
    School construction 2 1 Education 31/12/09 12/11/10 Completion and Acceptance of work 100% DRC WB 14,705 14,705 100% 18,655
    Socail Access Grant 2 1 SAG 15/12/09 31/07/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
  Summary for Community: Dharkeynta (3 detail records)
  SUM                     19,705 19,705   23,655
  El Aali Social Access Fund 2 1 SAG 15/01/10 04/11/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Action Plan 2 1 CAP 03/12/09 28/02/10   0% DRC WB 0 0   0
    Community Center 2 1 Infrastructure 31/01/10 25/11/10 Completion and Acceptance of work 100% DRC WB 14,886 14,882 100% 19,846
  Summary for Community: El Aali (3 detail records)
  SUM                     19,886 19,882   24,846
  Farlibaax community action plan 2 1 CAP 03/12/09 27/02/10 CAP Endorsed 100% DRC WB 0 0   0
    Community Center 2 1 Infrastructure 31/01/10 14/12/10 Completion and Acceptance of work 100% DRC WB 14,823 14,823 100% 19,083
    Social Access Grant 2 1 SAG 15/12/09 11/10/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
  Summary for Community: Farlibaax (3 detail records)
  SUM                     19,823 19,823   24,083
  Geedlabenaad Community Action plan 2 1 CAP 03/12/09 28/02/10 CAP Endorsed 100% DRC WB 0 0   0
    Construction of Irrigation System 2 1 Agriculture Extension 31/12/09 21/11/10 Submission of SAG financial report 100% DRC WB 14,690 14,690 100% 18,818
    Socail access Grant 2 1 SAG 15/12/09 31/07/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
  Summary for Community: Geedlabenaad (3 detail records)
  SUM                     19,690 19,690   23,818
  Hiraan Socail Access grant 2 1 SAG 15/12/09 31/07/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Action Plan 2 1 CAP 03/12/09 28/02/10 CAP Endorsed 100% DRC WB 0 0   0
    Health post 2 1 Health 31/12/09 12/11/10 Completion and Acceptance of work 100% DRC WB 13,796 13,796 100% 16,956
    Community Action Plan Updated 3 2 CAP 04/02/13 30/06/13 CAP Endorsed 100% DRC DFID 0 0   0
    Rehabilitation of three wells and road feeder 3 2 Water Supply 04/06/13 30/03/14 Community Self Evaluation 100% DRC DFID 14,816 15,000 101% 17,816
  Summary for Community: Hiraan (5 detail records)
  SUM                     33,612 33,796   39,772
  Hoyin Social Access Grant 2 1 SAG 15/01/09 31/07/10 Submission of SAG financial report 100% DRC DANIDA 5,000 5,000 100% 5,000
    community action plan 2 1 CAP 21/11/09 28/02/10 CAP Endorsed 100% DRC DANIDA 0 0   0
    Health post 2 1 Health 31/01/09 28/12/10 Completion and Acceptance of work 100% DRC WB 13,807 13,807 100% 17,017
  Summary for Community: Hoyin (3 detail records)
  SUM                     18,807 18,807   22,017
  Ilkacado Social Access Grant 2 1 SAG 31/01/10 31/07/10 Submission of SAG financial report 100% DRC DANIDA 5,000 5,000 100% 5,000
    Community Action Plan 2 1 CAP 03/12/09 27/02/10 CAP Endorsed 100% DRC DANIDA 0 0   0
    Constuction of Two Berkads 2 1 Water Supply 31/01/10 21/11/10 Submission of SAG financial report 100% DRC DANIDA 14,451 14,451 100% 18,151
    Waddi Embankment 3 2 Water Supply 04/06/13 20/05/14 Community Self Evaluation 100% DRC DFID 17,725 15,000 85% 20,725
    Community Action Plan Updated 3 2 CAP 24/03/13 02/06/13 CAP endorsed 100% DRC DFID 0 0   0
  Summary for Community: Ilkacado (5 detail records)
  SUM                     37,176 34,451   43,876
  Jaadle Community Action Plan 2 1 CAP 03/12/09 16/06/10 CAP Endorsed 100% DRC WB 0 0   0
    Construction of Irrigation System 2 1 Agriculture Extension 31/01/10 21/11/10 Completion and Acceptance of work 100% DRC WB 14,214 14,214 100% 18,443
    Social Access Grant 2 1 SAG 15/01/10 31/07/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
  Summary for Community: Jaadle (3 detail records)
  SUM                     19,214 19,214   23,443
  Jawiil Marketplace 2 1 Infrastructure 31/01/10 21/11/10 Completion and Acceptance of work 100% DRC DANIDA 14,513 14,513 100% 18,213
    Social Access Fund 2 1 SAG 31/01/10 31/07/10 Submission of SAG financial report 100% DRC DANIDA 5,000 5,000 100% 5,000
    Community Action Plan 2 1 CAP 03/12/09 27/02/10 CAP Endorsed 100% DRC DANIDA 0 0   0
    Water piping system 3 2 Water Supply 12/06/13 20/04/14 Community self assessment 100% DRC DFID 14,150 15,000 106% 18,580
    Community Action Plan Updated 3 2 CAP 20/03/13 28/05/13 CAP endorsed 100% DRC DFID 0 0   0
  Summary for Community: Jawiil (5 detail records)
  SUM                     33,663 34,513   41,793
  Macaan qaal community action plan 2 1 CAP 03/12/09 27/02/10 CAP Endorsed 100% DRC WB 0 0   0
    Construction of Irrigation System 2 1 Water Supply 31/01/10 21/11/10 Completion and Acceptance of work 100% DRC WB 14,690 14,690 100% 18,818
    Social Access Fund 2 1 SAG 15/01/10 31/07/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
  Summary for Community: Macaan qaal (3 detail records)
  SUM                     19,690 19,690   23,818
  Qoolaaw Construction of Irrigation System 2 1 Agriculture Extension 31/01/10 21/11/10 Completion and Acceptance of work 100% DRC WB 14,214 14,214 100% 20,763
    Social Access Grant 2 1 SAG 15/01/10 31/07/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Action Plan 2 1 CAP 03/12/09 27/02/10 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Qoolaaw (3 detail records)
  SUM                     19,214 19,214   25,763
  Qoydo Community Action Plan 2 1 CAP 03/12/09 23/03/10 CAP Endorsed 100% DRC WB 0 0   0
    Socail Access Grant 2 1 SAG 15/01/10 31/07/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Contruction of Irrigation System 2 1 Water Supply 15/01/10 21/11/10 Completion and Acceptance of work 100% DRC WB 14,629 14,629 100% 18,517
  Summary for Community: Qoydo (3 detail records)
  SUM                     19,629 19,629   23,517
  Quracleey Socail Access Grant 2 1 SAG 15/01/10 31/07/10 Submission of SAG financial report 100% DRC DANIDA 5,000 5,000 100% 5,000
    Community Action plan 2 1 CAP 03/12/09 01/03/10 CAP Endorsed 100% DRC DANIDA 0 0   0
    Construction of Primary School 2 1 Education 15/01/10 21/11/10 Completion and Acceptance of work 100% DRC DANIDA 14,625 14,625 100% 18,925
  Summary for Community: Quracleey (3 detail records)
  SUM                     19,625 19,625   23,925
  Raangaabo community Action plan 2 1 CAP 03/12/09 28/02/10 CAP Endorsed 100% DRC DANIDA 0 0   0
    School extention 2 1 Education 31/12/09 11/11/10 Completion and Acceptance of work 100% DRC DANIDA 14,616 14,616 100% 18,216
    Social Access Grant 2 1 SAG 15/12/09 16/10/10 Submission of SAG financial report 100% DRC DANIDA 5,000 5,000 100% 5,000
  Summary for Community: Raangaabo (3 detail records)
  SUM                     19,616 19,616   23,216
  Sugoow Social Access Grant 2 1 SAG 15/01/10 23/09/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Action Plan 2 1 CAP 03/12/09 27/02/10 CAP Endorsed 100% DRC WB 0 0   0
    Construction of Irrigation System 2 1 Agriculture Extension 31/01/10 23/11/10 Completion and Acceptance of work 100% DRC WB 14,000 14,000 100% 18,202
  Summary for Community: Sugoow (3 detail records)
  SUM                     19,000 19,000   23,202
  Trejante Social Access Grant 2 1 SAG 15/12/09 16/10/10 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Action Plan 2 1 CAP 21/11/09 16/02/10 CAP Endorsed 100% DRC WB 0 0   0
    Health post 2 1 Health 31/12/09 11/11/10 Completion and Acceptance of work 100% DRC WB 13,863 13,863 100% 17,373
  Summary for Community: Trejante (3 detail records)
  SUM                     18,863 18,863   22,373
Summary for District: Beletweyne (72 detail records)
SUM                     475,464 473,770   577,471
Berbera Abdal Social Access Fund 1 1 SAG 15/12/08 19/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Market 1 1 Infrastructure 17/04/08 14/02/09 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,500
    Community Action Plan Updated 2 2 CAP 09/05/09 17/05/09 CAP Endorsed 100% DRC WB 0 0   0
    Maternal and Child Health Center (MCH) 2 2 Health 14/03/09 08/12/09 Submission of SAG financial report 100% DRC WB 15,055 15,044 100% 18,055
  Summary for Community: Abdal (4 detail records)
  SUM                     35,055 35,044   41,555
  Barwaqo Community Revolving Fund 1 1 Income Generation 16/04/08 14/02/09 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,000
    Social Access Fund 1 1 SAG 15/12/08 30/04/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Action Plan Updated 2 2 CAP 12/08/09 12/08/09 CAP Endorsed 100% DRC WB 0 0   0
    Construction of Cummunity Center 2 2 Infrastructure 23/09/09 05/07/10 Submission of SAG financial report 100% DRC WB 15,007 15,007 100% 18,007
  Summary for Community: Barwaqo (4 detail records)
  SUM                     35,007 35,007   41,007
  Burao Sheik Social Access Fund 1 1 SAG 15/12/08 27/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Action Plan Updated 2 2 CAP 09/04/09 14/04/09 CAP Endorsed 100% DRC WB 0 0   0
    Community Centre 2 2 Infrastructure 09/04/09 16/04/10 Submission of SAG financial report 100% DRC WB 14,959 14,959 100% 17,959
  Summary for Community: Burao Sheik (3 detail records)
  SUM                     19,959 19,959   22,959
  Daroleh Community Centre 1 1 Infrastructure 15/04/08 21/02/09 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,000
    Social Access Fund 1 1 SAG 15/12/08 19/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Revolving Fund 2 2 Income Generation 11/04/09 21/04/10 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,000
    Community Action Plan Updated 2 2 CAP 11/04/09 16/04/09 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Daroleh (4 detail records)
  SUM                     35,000 35,000   41,000
  Doha Guban Irrigation System 1 1 Agriculture Extension 17/04/08 28/02/09 Submission of SAG financial report 100% DRC WB 7,000 7,000 100% 8,400
    Social Access Fund 1 1 SAG 15/12/08 11/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Health Post 1 1 Health 17/04/08 19/03/09 Submission of SAG financial report 100% DRC WB 7,999 7,999 100% 9,599
    Extention of Irrigation system 2 2 Agriculture Extension 17/05/09 05/10/10 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,000
    Community Action Plan Updated 2 2 CAP 13/05/09 18/05/09 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Doha Guban (5 detail records)
  SUM                     34,999 34,999   40,999
  Lafarug Social Access Fund 1 1 SAG 15/12/08 19/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Marketplace 1 1 Infrastructure 16/04/08 16/04/09 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,002
    Peace Center 2 2 Infrastructure 02/06/09 23/07/10 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,010
    Community Action Plan Updated 2 2 CAP 11/05/09 17/05/09 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Lafarug (4 detail records)
  SUM                     35,000 35,000   41,012
  Lalays Social Access Fund 1 1 SAG 15/12/08 11/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Water diversion 1 1 Environment 16/04/08 28/02/09 Submission of SAG financial report 100% DRC WB 14,981 14,981 100% 17,981
    Community Action Plan Updated 2 2 CAP 11/05/09 16/05/09 CAP Endorsed 100% DRC WB 0 0   0
    Primary School extension 2 2 Education 23/04/09 31/05/10 Submission of SAG financial report 100% DRC WB 14,982 14,982 100% 17,982
  Summary for Community: Lalays (4 detail records)
  SUM                     34,963 34,963   40,963
  Las'idle Health Post 1 1 Health 16/04/08 10/02/09 Submission of SAG financial report 100% DRC WB 9,500 9,500 100% 12,000
    Social Access Fund 1 1 SAG 15/12/08 27/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Revolving Fund 1 1 Income Generation 17/04/08 27/02/09 Submission of SAG financial report 100% DRC WB 5,500 5,500 100% 6,000
    Community Centre 2 2 Infrastructure 23/04/09 02/09/10 Submission of SAG financial report 100% DRC WB 9,991 9,991 100% 11,991
    Electricity 2 2 Infrastructure 15/04/09 28/10/10 Submission of SAG financial report 100% DRC WB 4,500 4,500 100% 5,000
    Community Action Plan Updated 2 2 CAP 15/04/09 20/04/09 CAP Endorsed 100% DRC WB 0 0   0
    Social Access Fund (Additional funding) 2 3 SAG 15/05/10 30/09/10 Submission of SAG financial report 100% DRC WB 3,000 3,000 100% 3,000
    School extension (Additional Funding) 2 3 Education 15/05/10 30/09/10 Completion and Acceptance of work 100% DRC WB 15,000 15,000 100% 18,728
  Summary for Community: Las'idle (8 detail records)
  SUM                     52,491 52,491   61,719
  Tulio Dhibijo Social Access Fund 1 1 SAG 15/12/08 27/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Latrines 1 1 Sanitation 15/03/08 29/04/09 Submission of SAG financial report 100% DRC WB 8,334 8,334 100% 10,002
    Health post and community center 2 2 Health 15/04/09 27/07/10 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 17,920
    Community Action Plan Updated 2 2 CAP 16/05/09 21/05/09 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Tulio Dhibijo (4 detail records)
  SUM                     28,334 28,334   32,922
  Waddajir Social Access Fund 1 1 SAG 15/12/08 19/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Revolving Fund 1 2 Income Generation 15/04/08 14/02/09 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,000
    Community centre 2 2 Infrastructure 02/06/09 10/06/10 Submission of SAG financial report 100% DRC WB 15,007 15,007 100% 18,007
    Community Action Plan Updated 2 2 CAP 09/05/09 14/05/09 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Waddajir (4 detail records)
  SUM                     35,007 35,007   41,007
Summary for District: Berbera (44 detail records)
SUM                     345,815 345,804   405,143
Boroma Abu Qyas Social Access Fund 1 1 SAG 15/12/08 26/04/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Health Post 1 1 Health 17/04/08 21/02/09 Submission of SAG financial report 100% DRC WB 11,450 11,450 100% 14,450
    Community Action Plan Updated 2 2 CAP 31/07/09 31/10/09 CAP Endorsed 100% DRC WB 0 0   0
    Farm Bunds 2 2 Agriculture Extension 16/08/09 03/09/10 Submission of SAG financial report 100% DRC WB 10,500 10,500 100% 13,525
    Water catchment (Dam) 2 2 Water Supply 16/08/09 03/09/10 Submission of SAG financial report 100% DRC WB 5,247 5,247 100% 6,247
  Summary for Community: Abu Qyas (5 detail records)
  SUM                     32,197 32,197   39,222
  Ceelabaxay Social Access Fund 1 1 SAG 15/12/08 10/04/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Irrigation System 1 1 Agriculture Extension 16/04/08 09/04/09 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 19,960
    Community Action Plan Updated 2 2 CAP 28/04/09 16/05/09 CAP Endorsed 100% DRC WB 0 0   0
    Gabions for soil erosion control 2 2 Environment 31/05/09 17/04/10 Submission of SAG financial report 100% DRC WB 3,030 3,030 100% 4,020
    Irrigation Extension 2 2 Agriculture Extension 31/05/09 26/03/10 Submission of SAG financial report 100% DRC WB 12,000 12,000 100% 14,000
  Summary for Community: Ceelabaxay (5 detail records)
  SUM                     35,030 35,030   42,980
  Holhol Social Access Fund 1 1 SAG 15/12/08 31/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    MCH 2 2 Health 09/08/09 15/08/10 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 17,777
    Community Action Plan Updated 2 2 CAP 28/04/09 16/05/09 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Holhol (3 detail records)
  SUM                     20,000 20,000   22,777
  Jir Jir Social Access Fund 1 1 SAG 15/12/08 19/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Health Post 1 1 Health 16/04/08 24/03/09 Submission of SAG financial report 100% DRC WB 11,000 11,000 100% 14,000
    Community Action Plan Updated 2 2 CAP 16/05/09 16/08/09 CAP Endorsed 100% DRC WB 0 0   0
    Community Revolving Funds 2 2 Income Generation 24/06/09 11/05/10 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,000
  Summary for Community: Jir Jir (4 detail records)
  SUM                     31,000 31,000   37,000
  Qalooc Social Access Fund 1 1 SAG 15/12/08 19/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Berkeds 1 1 Water Supply 17/04/08 23/04/09 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 21,372
    Berkeds 2 2 Water Supply 03/05/09 18/11/09 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 22,402
    Community Action Plan Updated 2 2 CAP 21/04/09 16/05/09 CAP Endorsed 100% DRC WB 0 0   0
    Social Access Fund (Additional Funding) 2 3 SAG 15/05/10 30/09/10 Instalment 1/1 Disbursed 100% DRC WB 3,000 3,000 100% 3,000
    2 Barkeds (Additional funding) 2 3 Water Supply 15/05/10 30/09/10 Completion and Acceptance of work 100% DRC WB 15,000 15,000 100% 19,341
  Summary for Community: Qalooc (6 detail records)
  SUM                     53,000 53,000   71,115
  Sh. Ahmed Salan Community Marketplace 1 1 Infrastructure 15/04/08 10/05/09 Submission of SAG financial report 100% DRC WB 15,000 17,023 113% 21,000
    Social Access Fund 1 1 SAG 15/12/08 19/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Action Plan Updated 2 2 CAP 11/05/09 18/08/09 CAP Endorsed 100% DRC WB 0 0   0
    Community Revolving Fund 2 2 Income Generation 11/05/09 01/05/10 Completion and Acceptance of work 100% DRC WB 15,000 15,000 100% 18,000
  Summary for Community: Sh. Ahmed Salan (4 detail records)
  SUM                     35,000 37,023   44,000
  Sh. Ali Jawar Social Access Fund 1 1 SAG 15/12/08 31/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Latrines 1 1 Sanitation 15/04/08 23/04/09 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,952
    Community Revolving Fund 2 2 Income Generation 25/04/09 29/07/10 Completion and Acceptance of work 100% DRC WB 15,000 15,000 100% 18,000
    Community Action Plan Updated 2 2 CAP 25/04/09 16/05/09 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Sh. Ali Jawar (4 detail records)
  SUM                     35,000 35,000   41,952
  Sh. Makhail Social Access Fund 1 1 SAG 15/12/08 30/04/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Extension of Primary School 1 1 Education 15/04/08 27/04/09 Submission of SAG financial report 100% DRC WB 14,518 14,518 100% 18,148
    Community Action Plan Updated 2 2 CAP 29/04/09 16/05/09 CAP Endorsed 100% DRC WB 0 0   0
    Community Revolving Fund 2 2 Income Generation 29/04/09 29/07/10 Completion and Acceptance of work 100% DRC WB 15,000 15,000 100% 18,000
  Summary for Community: Sh. Makhail (4 detail records)
  SUM                     34,518 34,518   41,148
  Sh. Osman Footbridge and Irish Crossing 1 1 Infrastructure 15/04/08 09/03/09 Submission of SAG financial report 100% DRC WB 14,979 14,979 100% 18,599
    Social Access Fund 1 1 SAG 15/12/08 19/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Revolving Fund 2 2 Income Generation 25/04/09 14/07/10 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,000
    Community Action Plan Updated 2 2 CAP 25/04/09 16/05/09 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Sh. Osman (4 detail records)
  SUM                     34,979 34,979   41,599
  Tulli Berkeds 1 1 Water Supply 17/04/08 30/04/09 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 21,372
    Social Access Fund 1 1 SAG 15/12/08 31/03/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Berkeds 2 2 Water Supply 03/05/09 14/11/09 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,000
    Community Action Plan Updated 2 2 CAP 19/04/09 16/05/09 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Tulli (4 detail records)
  SUM                     35,000 35,000   44,372
Summary for District: Boroma (43 detail records)
SUM                     345,724 347,747   426,165
Bossaso Afur-ur Health Post 1 1 Health 09/05/08 11/04/09 Submission of SAG financial report 100% DRC WB 13,150 13,150 100% 16,605
    Social Access Fund 1 1 SAG 25/01/08 15/06/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community hall 2 2 Infrastructure 04/05/09 31/12/09 Submission of SAG financial report 100% DRC WB 14,233 14,233 100% 17,791
    Community Action Plan Updated 2 2 CAP 08/01/09 31/07/09 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Afur-ur (4 detail records)
  SUM                     32,383 32,383   39,396
  Girible Social Access Fund 1 1 SAG 23/12/08 30/06/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Health Post 1 1 Health 09/05/08 30/06/09 Submission of SAG financial report 100% DRC WB 14,700 14,700 100% 18,107
    Marketplace 2 2 Infrastructure 12/08/09 20/08/10 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 19,000
    Community Action Plan Updated 2 2 CAP 11/07/09 16/07/09 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Girible (4 detail records)
  SUM                     34,700 34,700   42,107
  Hafatul Arab Social Access Fund 1 1 SAG 23/12/08 30/06/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Health Post 1 1 Health 11/05/08 30/06/09 Submission of SAG financial report 100% DRC WB 14,850 14,850 100% 18,500
    Community Action Plan Updated 2 2 CAP 07/07/09 12/07/09 CAP Endorsed 100% DRC WB 0 0   0
    Construction of School 2 2 Education 12/08/09 29/06/10 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 19,200
  Summary for Community: Hafatul Arab (4 detail records)
  SUM                     34,850 34,850   42,700
  Kalabayr Social Access Fund 1 1 SAG 23/12/08 30/06/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    School 1 1 Education 11/05/08 30/06/09 Submission of SAG financial report 100% DRC WB 7,200 3,600 50% 9,000
    Community Centre 2 2 Infrastructure 12/08/09 30/06/10 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 19,713
    School Extension 2 2 Education 12/08/09 30/06/10 Completion and Acceptance of work 100% DRC WB 9,000 9,000 100% 11,735
    Community Action Plan Updated 2 2 CAP 13/07/09 18/07/09 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Kalabayr (5 detail records)
  SUM                     36,200 32,600   45,448
  Karin Social Access Fund 1 1 SAG 25/01/09 30/06/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Latrine 1 1 Sanitation 11/12/08 30/06/09 Submission of SAG financial report 100% DRC WB 10,915 10,915 100% 13,465
    Community Action Plan Updated 2 2 CAP 14/07/09 19/07/09 CAP Endorsed 100% DRC WB 0 0   0
    Wells and Barkads 2 2 Agriculture Extension 12/08/09 30/06/10 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 20,400
  Summary for Community: Karin (4 detail records)
  SUM                     30,915 30,915   38,865
  Laag Social Access Fund 1 1 SAG 23/12/08 30/06/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Extension of School 1 1 Education 29/03/09 30/06/09 Submission of SAG financial report 100% DRC WB 7,200 7,200 100% 9,000
    School Extension 2 2 Education 12/08/09 30/06/10 Completion and Acceptance of work 100% DRC WB 9,000 9,000 100% 10,797
    Water Extension 2 2 Water Supply 12/01/10   Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,013
    Community Action Plan Updated 2 2 CAP 14/07/09 19/07/09 CAP Endorsed 100% DRC WB 0 0   0
  Summary for Community: Laag (5 detail records)
  SUM                     36,200 36,200   42,810
  Reebi Health Post 1 1 Health 09/05/08 31/03/09 Submission of SAG financial report 100% DRC WB 14,260 14,260 100% 17,703
    Social Access Fund 1 1 SAG 22/12/08 30/06/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Community Action Plan Updated 2 2 CAP 07/07/09 12/07/09 CAP Endorsed 100% DRC WB 0 0   0
    Marketplace 2 2 Infrastructure 12/08/09 30/06/10 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 21,000
  Summary for Community: Reebi (4 detail records)
  SUM                     34,260 34,260   43,703
  Soweto Social Access Fund 1 1 SAG 19/12/08 30/06/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Health Post 1 1 Health 12/05/08 30/06/09 Submission of SAG financial report 100% DRC WB 14,000 14,000 100% 17,301
    Community Action Plan Updated 2 2 CAP 17/07/09 22/07/09 CAP Endorsed 100% DRC WB 0 0   0
    Garbage Collection Pits 2 2 Sanitation 12/08/09 30/06/10 Submission of SAG financial report 100% DRC WB 14,066 14,066 100% 17,582
  Summary for Community: Soweto (4 detail records)
  SUM                     33,066 33,066   39,883
  Tasjic Social Access Fund 1 1 SAG 25/01/09 30/06/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    Water System 1 1 Water Supply 11/12/08 30/06/09 Submission of SAG financial report 100% DRC WB 14,990 14,990 100% 18,145
    Extention of School 2 2 Education 12/08/09 30/06/10 Submission of SAG financial report 100% DRC WB 15,000 15,000 100% 18,750
    Community Action Plan Updated 2 2 CAP 26/07/09 31/07/09 CAP Endorsed 100% DRC WB 0 0   0
    Community Center (Additional funding) 2 3 Infrastructure 15/05/10 30/10/10 Completion and Acceptance of work 100% DRC WB 15,000 15,000 100% 19,011
    Social Access Fund (Additional Funding) 2 3 SAG 15/05/10 30/10/10 Submission of SAG financial report 100% DRC WB 3,000 3,000 100% 3,000
  Summary for Community: Tasjic (6 detail records)
  SUM                     52,990 52,990   63,906
  Yalho Health Post 1 1 Health 15/05/08 15/06/09 Submission of SAG financial report 100% DRC WB 13,200 13,200 100% 16,255
    Social Access Fund 1 1 SAG 22/12/08 30/06/09 Submission of SAG financial report 100% DRC WB 5,000 5,000 100% 5,000
    School Extension 2 2 Education 12/08/09 30/06/10 Submission of SAG financial report 100% DRC WB 14,959 14,959 100% 18,699
    Community Action Plan Updated 2 2 CAP 09/07/09 09/07/09 CAP updated 100% DRC WB 0 0   0
  Summary for Community: Yalho (4 detail records)
  SUM                     33,159 33,159   39,954
Summary for District: Bossaso (44 detail records)
SUM                     358,723 355,123   438,772
Ceelafweyn Beerweyso Latrine construction 3 1 Sanitation 04/04/12     100% DRC DANIDA_RPLP 15,000 10,109 67% 15,000
    Berked construction 3 1 Water Supply 01/06/11 30/11/11 Installment 3/3 Disbursed 100% DRC DANIDA_RPLP 8,896 8,896 100% 12,004
    Community Action Plan 3 1 CAP 08/03/11 30/11/11 CAP Endorsed 100% DRC DANIDA_RPLP 0 0   0
    Community Center 3 1 Infrastructure 01/06/11 30/11/11 Installment 3/3 Disbursed 100% DRC DANIDA_RPLP 6,156 6,156 100% 7,578
    Community Action Plan Updated 3 2 CAP 10/12/11 29/02/12 CAP Endorsed 100% DRC DFID_II 0 0   0
    Berkad 2 roof catchment 3 2 Water Supply 04/04/12 19/06/12 Community Self Evaluation 100% DRC DFID_II 14,998 14,998 100% 19,523
  Summary for Community: Beerweyso (6 detail records)
  SUM                     45,050 40,158   54,105
  Bixin Community Action Plan Updated 3 2 CAP 04/01/12 04/01/12 CAP Endorsed 100% DRC DFID_II 0 0   0
    School construction 3 2 Education 02/02/12 03/06/12 Community Self Evaluation 100% DRC DFID_II 15,000 15,000 100% 19,336
  Summary for Community: Bixin (2 detail records)
  SUM                     15,000 15,000   19,336
  Bohol Construction of two Barkads 2 1 Water Supply 01/10/09 28/02/10 Completion and Acceptance of work 100% DRC DANIDA_PLIS 14,825 14,825 100% 14,825
    Community Action Plan 3 1 CAP 01/01/09 01/01/09 CAP drafted 100% DRC DANIDA_PLIS 0 0   0
    social Access Grant 3 2 SAG 12/10/13 28/10/13 Instalment 1/1 Disbursed 100% DRC EC 5,000 5,000 100% 5,000
    Construction of two berkads 3 2 Water Supply 17/07/12 27/12/12 Community Self Assessments 100% DRC EC 14,961 14,961 100% 20,930
    Community Action Plan Updated 3 2 CAP 14/02/12 14/02/12 CAP endorsed 100% DRC EC 0 0   0
  Summary for Community: Bohol (5 detail records)
  SUM                     34,786 34,786   40,755
  Ceelafwayn town Community Action Plan 2 1 CAP 01/01/09 02/01/09 CAP Endorsed 100% DRC DANIDA_PLIS 0 0   0
    Construction of roof catchment 2 1 Water Supply 02/02/09 31/10/10 Submission of SAG financial report 100% DRC Not Defined 0 15,000   0
    20 Roof Catchments with Berkads 3 1 Water Supply 01/01/10 31/05/11 Completion and Acceptance of work 100% DRC DANIDA_RPLP 14,990 14,990 100% 19,840
    Community Action Plan Updated 3 2 CAP 10/12/11 30/12/11 CAP Endorsed 100% DRC DFID_II 0 0   0
    15 Roof catchments 3 2 Water Supply 12/02/12 19/06/12 Community Self Evaluation 100% DRC DFID_II 15,000 14,994 100% 21,510
  Summary for Community: Ceelafwayn town (5 detail records)
  SUM                     29,990 44,984   41,350
  Ceellahelay Community Action Plan 3 1 CAP 08/03/11 31/12/11 CAP Endorsed 100% DRC DANIDA_RPLP 0 0   0
    1 big Barkad and 7 roof catchments 3 1 Water Supply 01/05/11 30/12/11 Community Self Evaluation 100% DRC DANIDA_RPLP 14,975 14,975 100% 19,887
    Community Centre 3 2 Infrastructure 09/05/12 02/08/12 Community Self Evaluation 100% DRC DFID_II 15,000 14,981 100% 18,294
    Community Action Plan Updated 3 2 CAP 10/12/11 15/01/12 CAP Endorsed 100% DRC DFID_II 0 0   0
  Summary for Community: Ceellahelay (4 detail records)
  SUM                     29,975 29,956   38,181
  Ceelmidgaan School construction 3 1 Education 16/08/11   Installment 1/3 Disbursed 100% DRC DANIDA_RPLP 0 15,000   0
    Community Action Plan 3 1 CAP 08/03/11 30/11/11 CAP Endorsed 100% DRC DANIDA_RPLP 0 0   0
    1 Berkad and 5 roof catchments 3 2 Water Supply 10/01/12 19/06/12 Community Self Evaluation 100% DRC DFID_II 14,745 14,745 100% 20,803
    Community Action Plan Updated 3 2 CAP 10/12/11 03/03/12 CAP Endorsed 100% DRC DFID_II 0 0   0
  Summary for Community: Ceelmidgaan (4 detail records)
  SUM                     14,745 29,745   20,803
  Dararweyne Community Action Plan 2 1 CAP 01/01/09 30/01/09 CAP drafted 100% DRC DANIDA_PLIS 0 0   0
    Community Center 2 1 Infrastructure 01/10/09 28/02/10 Completion and Acceptance of work 100% DRC DANIDA_PLIS 15,000 15,000 100% 15,000
    Construction of two berkads 3 2 Water Supply 02/02/12 31/12/12 Completion and Acceptance of Work 100% DRC EC 15,001 15,001 100% 21,189
    Social Access Grant 3 2 SAG 12/10/13 31/10/13 Instalment 1/1 Disbursed 100% DRC EC 5,000 5,000 100% 5,000
    Community Action Plan Updated 3 2 CAP 02/01/12 20/01/12 CAP Endorsed 100% DRC EC 0 0   0
  Summary for Community: Dararweyne (5 detail records)
  SUM                     35,001 35,001   41,189
  Dhabarmamac Construction of two Barkads 2 1 Water Supply 06/03/11 28/02/10 Completion and Acceptance of work 100% DRC DANIDA_PLIS 14,327 14,327 100% 14,327
    Community Action Plan 3 1 CAP 01/01/09 01/01/09 CAP Endorsed 100% DRC DANIDA_PLIS 0 0   0
    Construction of 2 berkads 3 2 Water Supply 20/06/12 13/03/13 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 21,016
    Community Action Plan Updated 3 2 CAP 14/02/12 20/12/12 CAP updated 100% DRC EC 0 0   0
    social Access Grant 3 2 SAG 12/10/13 28/10/13 Instalment 1/1 Disbursed 100% DRC EC 5,000 5,000 100% 5,000
  Summary for Community: Dhabarmamac (5 detail records)
  SUM                     34,327 34,327   40,343
  Dogoble Community Action Plan 2 1 CAP 01/01/09 30/01/09 CAP Endorsed 100% DRC DANIDA_PLIS 0 0   0
    Construction of two Barkads 2 1 Water Supply 01/10/09 28/02/10 Completion and Acceptance of work 100% DRC DANIDA_PLIS 14,164 14,164 100% 14,164
    Construction of berkads 3 2 Water Supply 18/07/12 27/12/12 Community Self Evaluation 100% DRC EC 14,979 14,979 100% 20,271
    social Access Grant 3 2 SAG 12/10/13 31/10/13 QAU Technical Review of Proposal 100% DRC EC 5,000 5,000 100% 5,000
    Community Action Plan Updated 3 2 CAP 14/02/12 28/02/12 CAP Endorsed 100% DRC EC 0 0   0
  Summary for Community: Dogoble (5 detail records)
  SUM                     34,144 34,144   39,436
  Gal iyo Qac Community Action Plan 3 1 CAP 08/03/11 31/12/11 CAP Endorsed 100% DRC DANIDA_RPLP 0 0   0
    Berkad construction 3 1 Water Supply 03/07/11 31/12/11 Completion and Acceptance of Work 100% DRC DANIDA_RPLP 14,433 14,433 100% 19,477
    Community Action Plan Updated 3 2 CAP 10/12/11 25/03/12 CAP Endorsed 100% DRC DFID_II 0 0   0
    2 Berkad construction 3 2 Water Supply 17/04/12 19/06/12 Community Self Evaluation 100% DRC DFID_II 15,000 15,000 100% 20,568
  Summary for Community: Gal iyo Qac (4 detail records)
  SUM                     29,433 29,433   40,045
  Garabcad Community Action Plan 3 1 CAP 08/03/11 15/04/11 CAP Endorsed 100% DRC DANIDA_RPLP 0 0   0
    Berkads 3 1 Water Supply 12/05/11 31/12/11 Community Self Evaluation 100% DRC DANIDA_RPLP 13,848 13,848 100% 17,386
    Community Action Plan Updated 3 2 CAP 10/12/11 04/03/12 CAP updated 100% DRC DFID_II 0 0   0
    Community Center 3 2 Infrastructure 09/04/12 06/06/12 Community Self Evaluation 100% DRC DFID_II 14,984 14,981 100% 18,278
  Summary for Community: Garabcad (4 detail records)
  SUM                     28,832 28,829   35,664
  God caanood Berkad and Irrigation Canal 3 1 Agriculture Extension 26/09/10 21/02/11 Completion and Acceptance of work 100% DRC DANIDA_RPLP 14,940 14,940 100% 18,661
    Community Action Plan 3 1 CAP 26/09/10 31/05/11 CAP Endorsed 100% DRC DANIDA_RPLP 0 0   0
    School extension 3 2 Education 02/02/12 19/06/12 Community Self Evaluation 100% DRC DFID_II 15,000 15,000 100% 19,335
    Community Action Plan Updated 3 2 CAP 10/12/11 08/01/12 CAP endorsed 100% DRC DFID_II 0 0   0
  Summary for Community: God caanood (4 detail records)
  SUM                     29,940 29,940   37,996
  Hamilka Community Action Plan 2 1 CAP 01/01/09 30/01/09 CAP drafted 100% DRC DANIDA_PLIS 0 0   0
    Barkats 2 1 Water Supply 01/10/09 28/02/10 Submission of SAG financial report 100% DRC DANIDA_PLIS 0 14,991   0
    Construction of two berkads 3 2 Water Supply 02/02/12 21/10/12 Community Self Evaluation 100% DRC EC 15,000 15,000 100% 20,400
    Community Action Plan Updated 3 2 CAP 14/02/12 25/10/12 CAP Endorsed 100% DRC EC 0 0   0
    social Access Grant 3 2 SAG 12/10/13 28/10/13 Submission of SAG financial report 100% DRC EC 5,000 5,000 100% 5,000
  Summary for Community: Hamilka (5 detail records)
  SUM                     20,000 34,991   25,400
  Huluul Community Action Plan 3 1 CAP 26/09/10 31/05/11 CAP Endorsed 100% DRC DANIDA_RPLP 0 0   0
    School Extension 3 1 Education 26/09/10 31/05/11 Installment 2/3 disbursed 100% DRC DANIDA_RPLP 15,000 15,000 100% 19,037
  Summary for Community: Huluul (2 detail records)
  SUM                     15,000 15,000   19,037
  Kalsheik School Extension 3 1 Education 26/09/10 31/05/11 Completion and Acceptance of work 100% DRC DANIDA_RPLP 15,000 15,000 100% 18,729
    Community Action Plan 3 1 CAP 26/09/10 31/05/11 CAP Endorsed 100% DRC DANIDA_RPLP 0 0   0
    Community Action Plan Updated 3 2 CAP 10/12/11 16/12/12 CAP endorsed 100% DRC DFID_II 0 0   0
    Community Centre 3 2 Infrastructure 02/02/12 30/07/12 Community Self Evaluation 100% DRC DFID_II 15,000 14,982 100% 18,294
  Summary for Community: Kalsheik (4 detail records)
  SUM                     30,000 29,982   37,023
  Sin-Caro School Extension 3 1 Education 26/09/10 31/05/11 Completion and Acceptance of work 100% DRC DANIDA_RPLP 15,000 15,000 100% 19,037
    Community Action Plan 3 1 CAP 26/09/10 31/05/11 CAP Endorsed 100% DRC DANIDA_RPLP 0 0   0
    15 Roof catchments 3 2 Water Supply 17/04/12 04/07/12 Community Self Evaluation 100% DRC DFID_II 14,994 14,994 100% 21,504
    Community Action Plan Updated 3 2 CAP 10/12/11 31/12/11 CAP Endorsed 100% DRC DFID_II 0 0   0
  Summary for Community: Sin-Caro (4 detail records)
  SUM                     29,994 29,994   40,541
Summary for District: Ceelafweyn (68 detail records)
SUM                     456,215 496,269   571,203
Dolo_Ado Amino CAP 1 1 CAP 18/06/13 26/07/13 Finance activity 100% DRC DANIDA_2013 0 0   0
  Summary for Community: Amino (1 detail records)
  SUM                     0 0   0
  Goysin (Suftu Kebele) To be determind 1 1 Education 01/11/13     0% DRC DANIDA 0 0   0
    Community Action Plan 1 1 CAP 12/06/13 30/09/13   100% DRC DANIDA_2013 0 0   0
  Summary for Community: Goysin (Suftu Kebele) (2 detail records)
  SUM                     0 0   0
  Kilimesenge (Suftu Kebele) CAP 1 1 CAP 17/06/13 27/09/13   0% Not Defined DANIDA 0 0   0
  Summary for Community: Kilimesenge (Suftu Kebele) (1 detail records)
  SUM                     0 0   0
  Megeg (Suftu Kebele) CAP 1 1 Education 13/06/13 26/09/13   0% Not Defined DANIDA 0 0   0
  Summary for Community: Megeg (Suftu Kebele) (1 detail records)
  SUM                     0 0   0
Summary for District: Dolo_Ado (5 detail records)
SUM                     0 0   0
Dolow Abdiwahid Community action plan updated 2 4 Infrastructure 21/04/15 30/06/15 CAP Endorsed 0% DRC MFA-Finland 0 0   0
    Street Light 4 1 Infrastructure 05/08/14 31/12/14 3\3 Installment Disbused 100% DRC MFA-Finland 16,950 0 0% 21,209
    Community Action Plan 4 1 CAP 02/03/14 24/07/14 CAP Endorsed 100% DRC MFA-Finland 0 0   0
    Solar Light 4 2 Infrastructure 10/06/15 30/06/15 3/3 Installment Disbursed 100% DRC MFA-Finland 0 0   0
  Summary for Community: Abdiwahid (4 detail records)
  SUM                     16,950 0   21,209
  Abore School Construction 4 1 Education 05/08/14 31/12/14 3/3 Installment Disbursed 100% DRC MFA-Finland 16,993 0 0% 21,253
    Community Action Plan 4 1 CAP 01/01/14 24/07/14 Endorsed CAP 100% DRC MFA-Finland 0 0   0
    Community action plan updated 4 2 Infrastructure 07/04/15 30/06/15 CAP endorsed 0% Not Defined MFA-Finland 0 0   0
    Community center 4 2 Infrastructure 30/03/15 30/06/15 3/3 Installment Disbursed 100% DRC MFA-Finland 0 0   0
  Summary for Community: Abore (4 detail records)
  SUM                     16,993 0   21,253
  Dhudhumey Community Center 4 1 Infrastructure 05/08/14 31/12/14 3/3 Installment Disbursed 100% DRC MFA-Finland 16,916 16,916 100% 21,166
    Community Action Plan 4 1 CAP 15/07/14 24/07/14 Endorsed CAP 100% DRC MFA-Finland 0 0   0
    contruction of school 4 2 Education 30/04/15 30/06/15 3/3 Installment Disbursed 100% DRC Not Defined 0 0   0
    Community action plan updated 4 2 Education 07/01/15 25/02/15 CAP Endorsed 0% DRC MFA-Finland 0 0   0
  Summary for Community: Dhudhumey (4 detail records)
  SUM                     16,916 16,916   21,166
  Farah Ali Gule Construction of Street Lights 4 1 Infrastructure 05/08/14 31/12/14 2\3 Installment Disbused 100% DRC MFA-Finland 16,950 0 0% 21,209
    Community Action Plan 4 1 CAP 31/03/14 24/07/14 CAP Endorsed 100% DRC MFA-Finland 0 0   0
    Solar Light 4 2 Not Defined 30/03/15 30/06/15 3\3 Installment Disbused 40% DRC MFA-Finland 0 0   0
    Community action plan updated 4 2 Infrastructure 04/01/15 30/06/15 CAP Endorsed 100% DRC MFA-Finland 0 0   0
  Summary for Community: Farah Ali Gule (4 detail records)
  SUM                     16,950 0   21,209
  Gedwayne Community Action Plan 4 1 CAP 17/03/14 27/03/14 Endorsed CAP 100% DRC MFA-Finland 0 0   0
    New school construction 4 1 Education 20/05/14 31/12/14 3\3 Installment Disbursed 100% DRC MFA-Finland 16,891 13,513 80% 21,845
    Community action plan updated 4 2 Education 06/01/15 26/02/15 CAP Endorsed 100% DRC MFA-Finland 0 0   0
    School construction 4 2 Not Defined 09/03/15 30/06/15 3/3 Installment Disbursed 0% Not Defined MFA-Finland 0 0   0
  Summary for Community: Gedwayne (4 detail records)
  SUM                     16,891 13,513   21,845
  Gondhoboow Community Action Plan 4 1 CAP 29/07/14 31/08/14 Endorsed CAP 100% DRC MFA-Finland 0 0   0
    Road Rehabilitation 4 1 Infrastructure 27/07/14 31/12/14 3/3 Installment Disbursed 100% DRC MFA-Finland 16,994 0 0% 19,770
    Community action plan updated 4 2 Infrastructure 05/01/15 24/03/15 CAP Endorsed 100% DRC MFA-Finland 0 0   0
    Community Center 4 2 Infrastructure 30/03/15 30/06/15 3\3 Installment Disbused 100% Not Defined MFA-Finland 0 0   0
  Summary for Community: Gondhoboow (4 detail records)
  SUM                     16,994 0   19,770
  Hamare School Consrtuction 4 1 Education 20/05/14 31/12/14 3/3 Instalment Disbursed 100% DRC MFA-Finland 16,993 16,993 100% 21,253
    Community Action Plan 4 1 CAP 13/07/14 17/07/14 Endorsed CAP 100% DRC MFA-Finland 0 0   0
    Community action plan updated 4 2 CAP 05/01/15 24/03/15 CAP Endorsed 100% DRC MFA-Finland 0 0   0
    Community Center 4 2 Infrastructure 10/06/15   3\3 Installment Disbused 100% DRC MFA-Finland 0 0   0
  Summary for Community: Hamare (4 detail records)
  SUM                     16,993 16,993   21,253
  Koorey Community Action Plan 4 1 CAP 04/05/14 18/05/14 Endorsed CAP 100% DRC MFA-Finland 0 0   0
    Heath Post 4 1 Health 21/05/14 31/12/14 3/3 Installment Disbursed 100% DRC MFA-Finland 16,993 16,993 100% 21,121
    Community action plan updated 4 2 CAP 06/01/15 30/06/15 CAP Endorsed 100% Not Defined MFA-Finland 0 0   0
    construction of Health post 4 2 Health 24/03/15 30/06/15 CAP Endorsed 100% DRC MFA-Finland 0 0   0
  Summary for Community: Koorey (4 detail records)
  SUM                     16,993 16,993   21,121
  Kurtin Community Action Plan 4 1 CAP 13/07/14 24/07/14 Endorsed CAP 100% DRC MFA-Finland 0 0   0
    Canal 4 1 Water Supply 27/07/14 31/12/14 3/3 Installment Disbursed 100% DRC MFA-Finland 16,830 16,830 100% 21,150
    School construction 4 2 Education 30/04/15 30/06/15 3/3 Installment Disbursed 100% DRC MFA-Finland 0 0   0
    Community action plan updated 4 2 CAP 04/01/15 10/03/15 CAP endorsed 100% DRC MFA-Finland 0 0   0
  Summary for Community: Kurtin (4 detail records)
  SUM                     16,830 16,830   21,150
  Qansaxley Community Action Plan 4 1 CAP 30/12/13 27/03/14 CAP Endorsed 100% DRC MFA-Finland 0 0   0
    Health Post 4 1 Health 21/05/14 31/07/14 3\3 Installment Disbused 100% DRC MFA-Finland 16,993 16,993 100% 21,121
    Community action plan updated 4 2 CAP 01/01/15 31/03/15 3/3 Installment Disbursed 100% DRC MFA-Finland 0 0   0
    Market 4 2 Infrastructure 06/01/15 30/06/15 3/3 Installment Disbursed 100% DRC MFA-Finland 0 0   0
  Summary for Community: Qansaxley (4 detail records)
  SUM                     16,993 16,993   21,121
  Qurdubay Community Action Plan 4 1 CAP 29/09/13 27/03/14 Endorsed CAP 100% DRC MFA-Finland 0 0   0
    School Construction 4 1 Education 20/05/14 31/08/14 3/3 Instalment Disbursed 100% DRC MFA-Finland 16,993 16,993 100% 21,253
    Health Post 4 2 Health 21/04/15 30/06/15 3/3 Installment Disbursed 100% DRC MFA-Finland 0 0   0
    Community action plan updated 4 2 CAP 05/01/15 31/03/15 CAP Endorsed 100% DRC MFA-Finland 0 0   0
  Summary for Community: Qurdubay (4 detail records)
  SUM                     16,993 16,993   21,253
  Sadhumey Health Post 4 1 Health 21/05/14 10/12/14 3\3 Installment Disbursed 100% DRC MFA-Finland 16,993 16,993 100% 21,121
    Community Action Plan 4 1 CAP 27/01/14 27/03/14 CAP Endorsed 100% DRC MFA-Finland 0 0   0
    School construction 4 2 Education 01/04/15 30/06/15 3/3 Installment Disbursed 100% DRC MFA-Finland 0 0   0
    Community action plan updated 4 2 CAP 01/01/15 31/03/15 CAP Endorsed 100% DRC MFA-Finland 0 0   0
  Summary for Community: Sadhumey (4 detail records)
  SUM                     16,993 16,993   21,121
  Surguduud Health Post 4 1 Health 21/05/14 20/10/14 3\3 Installment Disbused 100% DRC MFA-Finland 16,993 16,993 100% 21,121
    Community Action Plan 4 1 CAP 23/06/13 27/03/14 CAP Endorsed 100% DRC MFA-Finland 0 0   0
    Community cener construction 4 2 Infrastructure 30/04/15 30/06/15 3/3 Installment Disbursed 100% DRC MFA-Finland 0 0   0
    Community action plan updated 4 2 CAP 01/01/15 30/03/15 CAP endorsed 100% DRC MFA-Finland 0 0   0
  Summary for Community: Surguduud (4 detail records)
  SUM                     16,993 16,993   21,121
  Una Community Center 4 1 Infrastructure 21/05/14 05/10/14 3\3 Installment Disbused 100% DRC MFA-Finland 16,917 16,917 100% 21,167
    Community Action Plan 4 1 CAP 29/10/13 27/03/14 CAP Endorsed 100% DRC MFA-Finland 0 0   0
    School construction 4 2 Education 30/04/15 30/06/15 3/3 Installment Disbursed 100% DRC MFA-Finland 0 0   0
    Community action plan updated 4 2 CAP 01/01/15 30/03/15 CAP endorsed 100% Not Defined MFA-Finland 0 0   0
  Summary for Community: Una (4 detail records)
  SUM                     16,917 16,917   21,167
  Unsi A shallow Well with A pump and Elevated Water Tank 4 1 Water Supply 21/05/14 25/09/14 3\3 Installment Disbused 100% DRC MFA-Finland 16,993 0 0% 21,243
    Community Action Plan 4 1 CAP 29/08/13 27/03/14 CAP Endorsed 100% DRC MFA-Finland 0 0   0
    Community center construction 4 2 Not Defined 30/04/15 30/06/15 3/3 Installment Disbursed 100% Not Defined MFA-Finland 0 0   0
    Community action plan updated 4 2 Education 01/01/15 30/03/15 CAP Endorsed 100% DRC MFA-Finland 0 0   0
  Summary for Community: Unsi (4 detail records)
  SUM                     16,993 0   21,243
  Wadagey Canal Rehabilitation and construction of 4basement 4 1 Water Supply 27/07/14 31/12/14 Proposal Formulation 20% DRC MFA-Finland 16,830 0 0% 21,150
    Community Action Plan 4 1 CAP 20/02/14 24/07/14 Endorsed CAP 100% DRC MFA-Finland 0 0   0
    School construction 4 2 Infrastructure 30/04/15 30/06/15 3/3 Installment Disbursed 100% DRC MFA-Finland 0 0   0
    Community action plan updated 4 2 CAP 29/01/15 30/03/15 CAP endorsed 100% DRC MFA-Finland 0 0   0
  Summary for Community: Wadagey (4 detail records)
  SUM                     16,830 0   21,150
Summary for District: Dolow (64 detail records)
SUM                     271,223 166,134   338,152
Faraweyne Abdi Samad Community Action Plan 4 1 CAP 27/01/13 28/07/13 CAP endorsed 100% DRC DANIDA 0 0   0
    Berkad Rehabilitation 4 1 Water Supply 20/11/13 29/01/14 Community Self Evaluation 100% DRC DANIDA 16,999 16,998 100% 22,332
  Summary for Community: Abdi Samad (2 detail records)
  SUM                     16,999 16,998   22,332
  Aburin Community Action Plan 4 1 CAP 05/11/13 06/11/13 CAP endorsed 100% DRC DANIDA 0 0   0
    Berkat Rehab 4 1 Water Supply 06/10/13 06/01/14 Community Self Evaluation 100% DRC DANIDA 16,997 16,997 100% 21,080
  Summary for Community: Aburin (2 detail records)
  SUM                     16,997 16,997   21,080
  Aromadow Construction of three berkads 4 1 Water Supply 10/12/13 29/01/14 Community Self Evaluation 100% DRC DANIDA 17,000 17,000 100% 27,675
    Community Action Plan 4 1 CAP 24/01/13 12/08/13 CAP endorsed 100% DRC DANIDA 0 0   0
    Berkat Rehab 4 2 Water Supply 21/05/14 10/11/14 3rd Installment disbursement 100% DRC DANIDA 17,000 17,000 100% 21,014
    Community Action Plan Updated 4 2 CAP 27/04/14 29/05/14 CAP endorsed 100% DRC DANIDA 0 0   0
  Summary for Community: Aromadow (4 detail records)
  SUM                     34,000 34,000   48,689
  Aydrosh Community Action Plan 4 1 CAP 03/03/13 13/05/13 CAP endorsed 100% DRC MFA-Netherlands 0 0   0
    School Extension 4 1 Education 11/02/14 27/05/14 Community Self Evaluation 100% DRC MFA-Netherlands 16,986 16,986 100% 20,107
    Community Action Plan Updated 4 2 CAP 05/08/14   CAP endorsed 100% DRC MFA-Netherlands 0 0   0
    Community Center 4 2 Infrastructure 05/08/14   Completion and Acceptance of Work 0% DRC MFA-Netherlands 0 0   0
  Summary for Community: Aydrosh (4 detail records)
  SUM                     16,986 16,986   20,107
  Banderaman Community Action Plan 4 1 CAP 28/01/13 12/08/13 CAP endorsed 100% DRC MFA-Netherlands 0 0   0
    Construction of Community center 4 1 Infrastructure 26/09/13 25/02/14 Community Self Evaluation 100% DRC MFA-Netherlands 16,999 16,999 100% 21,107
    School Rehab/Extension 4 2 Education 05/08/14   Community Self Evaluation 0% DRC MFA-Netherlands 0 0   0
    Community Action Plan UPdated 4 2 CAP 05/08/14   CAP endorsed 0% DRC MFA-Netherlands 0 0   0
  Summary for Community: Banderaman (4 detail records)
  SUM                     16,999 16,999   21,107
  Da'arta Community Action Plan 4 1 CAP 14/07/13 16/07/13 CAP endorsed 100% DRC DANIDA 0 0   0
    Rehabilitation and Extention of School 4 1 Education 10/11/13 29/01/14 Community Self Evaluation 100% DRC DANIDA 17,000 17,000 100% 20,957
  Summary for Community: Da'arta (2 detail records)
  SUM                     17,000 17,000   20,957
  Dabolaq School Rehab 4 1 Education 12/02/14 08/06/14 Community Self Evaluation 100% DRC MFA-Netherlands 16,962 16,962 100% 20,517
    Community Action Plan 4 1 CAP 03/03/13 13/05/13 CAP endorsed 100% DRC MFA-Netherlands 0 0   0
    Community Action Plan Updated 4 2 CAP 10/08/14   CAP updated 0% DRC MFA-Netherlands 0 0   0
    Community Center 4 2 Not Defined 18/12/14 30/06/15 Completion and Acceptance of Work 100% DRC MFA-Netherlands 16,970 16,970 100% 21,078
  Summary for Community: Dabolaq (4 detail records)
  SUM                     33,932 33,932   41,595
  Farawine town School Extention/Rehabilitation 4 1 Education 21/10/13 17/03/14 Community Self Evaluation 100% DRC MFA-Netherlands 16,998 16,998 100% 20,886
    Community Action Plan 4 1 CAP 08/04/13 30/05/13 CAP endorsed 100% DRC MFA-Netherlands 0 0   0
    Community Action Plan Updated 4 2 CAP 07/09/14 23/09/14 CAP endorsed 0% DRC MFA-Netherlands 0 0   0
    Community Center 4 2 Infrastructure 05/08/14   Completion and Acceptance of Work 0% DRC DANIDA 0 0   0
  Summary for Community: Farawine town (4 detail records)
  SUM                     16,998 16,998   20,886
  Gadhyogol School Extention/Rehavilitation 4 1 Education 04/09/13 06/01/14 Community Self Evaluation 100% DRC DANIDA 17,000 17,000 100% 20,564
    Community Action Plan 4 1 CAP 21/04/13 20/05/13 CAP endorsed 100% DRC DANIDA 0 0   0
    Community Action Plan Updated 4 2 CAP 01/04/14 15/04/14 CAP endorsed 100% DRC DANIDA 0 0   0
    Berkad rehabII 4 2 Water Supply 25/05/14 20/11/14 3rd Installment disbursement 100% DRC DANIDA 16,997 16,997 100% 20,614
  Summary for Community: Gadhyogol (4 detail records)
  SUM                     33,997 33,997   41,179
  Garabis Community Action Plan 4 1 CAP 07/02/13 12/08/13 CAP endorsed 100% DRC DANIDA 0 0   0
    Berkad Rehab 4 1 Water Supply 18/12/13 29/01/14 Community Self Evaluation 100% DRC DANIDA 17,000 17,000 100% 20,431
  Summary for Community: Garabis (2 detail records)
  SUM                     17,000 17,000   20,431
  Goryo Berkat Rehab 4 1 Water Supply 03/09/13 06/01/14 Community Self Evaluation 100% DRC DANIDA 16,999 16,999 100% 21,795
    Community Action Plan 4 1 CAP 09/01/13 14/07/13 CAP endorsed 100% DRC DANIDA 0 0   0
    Community Action Plan Updated 4 2 CAP 01/04/14 10/04/14 CAP endorsed 100% DRC DANIDA 0 0   0
    Berkat Rehab II 4 2 Water Supply 25/05/14 20/11/14 3rd Installment disbursement 100% DRC DANIDA 16,999 13,599 80% 22,756
  Summary for Community: Goryo (4 detail records)
  SUM                     33,998 30,598   44,550
  GulAllaa Community Action Plan 4 1 CAP 06/11/13 15/11/13 CAP endorsed 100% DRC Not Defined 0 0   0
    Rehabilitation and Construction of Class rooms 4 1 Education 22/10/13 29/01/14 Community Self Evaluation 100% DRC DANIDA 16,997 16,997 100% 21,071
  Summary for Community: GulAllaa (2 detail records)
  SUM                     16,997 16,997   21,071
  Shimbiralle community Action Plan 4 1 CAP 05/11/13 15/11/13 CAP endorsed 100% DRC DANIDA 0 0   0
    Construction of Class rooms 4 1 Education 02/12/13 29/01/14 Community Self Evaluation 100% DRC DANIDA 17,000 17,000 100% 20,876
    Berkat Rehab 4 2 Water Supply 25/05/14 10/11/14 3rd Installment disbursement 70% DRC DANIDA 17,000 17,000 100% 27,296
    Community Action Plan Updated 4 2 CAP 01/04/14 10/04/14 CAP endorsed 100% DRC DANIDA 0 0   0
  Summary for Community: Shimbiralle (4 detail records)
  SUM                     34,000 34,000   48,172
  Wado bariis Community center 4 1 Infrastructure 26/09/13 14/01/14 Community Self Evaluation 100% DRC DANIDA 16,999 16,999 100% 21,107
    Community Action Plan 4 1 CAP 21/04/13 20/05/13 CAP endorsed 100% DRC DANIDA 0 0   0
    Community Action Plan Updated 4 2 CAP 27/04/14 29/05/14 CAP endorsed 80% DRC DANIDA 0 0   0
    Berkad Rehab II 4 2 Water Supply 10/08/14   Completion and Acceptance of Work 0% DRC DANIDA 0 0   0
  Summary for Community: Wado bariis (4 detail records)
  SUM                     16,999 16,999   21,107
  Wado makahil Community Action Plan 4 1 CAP 03/03/13 13/05/13 CAP endorsed 100% DRC MFA-Netherlands 0 0   0
    Community centre 4 1 Infrastructure 23/10/13 17/03/13 Community Self Evaluation 100% DRC MFA-Netherlands 17,000 17,000 100% 21,026
    Community Action Plan UPdated 4 2 CAP 07/09/14 23/09/14 CAP updated 0% DRC MFA-Netherlands 0 0   0
    School extension 4 2 Education 05/08/14   Community Self Evaluation 0% DRC MFA-Netherlands 0 0   0
  Summary for Community: Wado makahil (4 detail records)
  SUM                     17,000 17,000   21,026
Summary for District: Faraweyne (50 detail records)
SUM                     339,901 336,500   434,289
Galdogob Darasalam MCH 4 1 Health 02/09/13 27/12/13 community self evaluation 100% DRC EC 16,939 16,972 100% 20,233
    Community Action Plan 4 1 CAP 21/12/12 03/02/13 CAP Endorsed 100% DRC EC 0 0   0
  Summary for Community: Darasalam (2 detail records)
  SUM                     16,939 16,972   20,233
  Hawlwadaag Water Tank 1 1 Water Supply 22/10/13 30/12/13 Completion and Acceptance of work 100% DRC EC 16,159 16,978 105% 19,552
    Community Action Plan 4 1 CAP 21/12/12 18/03/13 CAP Drafted 100% DRC EC 0 0   0
  Summary for Community: Hawlwadaag (2 detail records)
  SUM                     16,159 16,978   19,552
  Hero Jaalle Community Action Plan 4 1 CAP 08/10/13 31/12/13 Endorsed CAP 100% DRC MFA-Netherlands 0 0   0
    Health Post 4 1 Health 02/03/13 30/06/14 Community Self Evaluation 100% DRC MFA-Netherlands 16,996 16,972 100% 20,240
    Community Action Plan Updated 4 2 CAP 10/08/14 11/08/14 CAP Updated 100% DRC MFA-Netherlands 0 0   0
    School Construction 4 2 Education 25/10/14 22/01/15 3/3 Instalment Disbursed 90% DRC MFA-Netherlands 17,000 17,000 100% 21,223
  Summary for Community: Hero Jaalle (4 detail records)
  SUM                     33,995 33,972   41,462
  Horseed Community Action Plan 4 1 CAP 21/12/12 20/03/13 CAP Endorsed 100% DRC EC 0 0   0
    Community Center 4 1 Infrastructure 04/09/13 31/12/13 Completion and Acceptance of work 100% DRC EC 16,985 16,880 99% 20,785
  Summary for Community: Horseed (2 detail records)
  SUM                     16,985 16,880   20,785
  Isqanbuus Community Action Plan 4 1 CAP 18/03/13 31/12/13 CAP Drafted 100% DRC EC 0 0   0
    Community Center 4 1 Environment 08/12/13 31/12/13 Community Self Evaluation 100% DRC EC 16,905 16,926 100% 20,705
  Summary for Community: Isqanbuus (2 detail records)
  SUM                     16,905 16,926   20,705
  Lanmadow Community Action Plan 4 1 CAP 25/12/13 30/01/14 CAP Endorsed 100% DRC MFA-Netherlands 0 0   0
    Community Center 4 1 Infrastructure 03/03/14 30/06/14 Community Self Evaluation 100% DRC MFA-Netherlands 16,974 16,974 100% 20,524
    Community Action Plan Updated 4 2 CAP 07/08/14 09/08/14   100% DRC DFID 0 0   0
    Health Post 4 2 Health 25/10/14 27/01/15 2/3 Installment Disbursed 100% DRC MFA-Netherlands 16,969 16,969 100% 20,862
  Summary for Community: Lanmadow (4 detail records)
  SUM                     33,943 33,943   41,386
  Qansaxle Community Action Plan 4 1 CAP 09/10/13 13/02/14 CAP Endorsed 100% DRC MFA-Netherlands 0 0   0
    School construction 4 1 Education 02/03/13 13/07/14 Community Self Evaluation 100% DRC MFA-Netherlands 16,982 16,989 100% 20,226
    Community Action Plan Updated 4 2 CAP 09/08/14 10/08/14 Endorsed CAP 100% DRC MFA-Netherlands 0 0   0
    Health Post 4 2 Health 25/10/14 25/01/15 3/3 Installment Disbursed 95% DRC MFA-Netherlands 16,975 16,975 100% 20,868
  Summary for Community: Qansaxle (4 detail records)
  SUM                     33,957 33,964   41,093
  Riig-Omane Community Centre 4 1 Health 09/03/13 30/06/14 Community Self Evaluation 100% DRC MFA-Netherlands 16,973 16,941 100% 20,523
    Community Action Plan 4 1 CAP 09/10/13 22/01/14 CAP Drafted 100% DRC MFA-Netherlands 0 0   0
    Community Action Plan Updated 4 2 CAP 09/08/14 15/08/14 Endorsed CAP 100% DRC MFA-Netherlands 0 0   0
    Health Post 4 2 Health 25/10/14 22/01/15 3/3 Installment Disbursed 20% DRC MFA-Netherlands 16,980 0 0% 20,723
  Summary for Community: Riig-Omane (4 detail records)
  SUM                     33,953 16,941   41,246
  Sayidka Community Center 4 1 Infrastructure 03/09/13 18/12/13 Community Self Evaluation 100% DRC EC 16,985 16,973 100% 20,785
    Community Action Plan 4 1 CAP 19/12/12 18/03/13 CAP endorsed 100% DRC EC 0 0   0
  Summary for Community: Sayidka (2 detail records)
  SUM                     16,985 16,973   20,785
  Wabari Community Action Plan 4 1 CAP 19/12/12 23/03/13 CAP Endorsed 100% DRC EC 0 0   0
    Community Center 4 1 Infrastructure 02/09/13 18/12/13 community self evaluation 100% DRC EC 16,985 16,973 100% 24,180
  Summary for Community: Wabari (2 detail records)
  SUM                     16,985 16,973   24,180
Summary for District: Galdogob (28 detail records)
SUM                     236,806 220,521   291,426
Garsila Damrat Qhoz Haimait CAP 1 1 Not Defined 20/12/12 20/12/12 PICD 100% DRC Not Defined 0 0   0
  Summary for Community: Damrat Qhoz Haimait (1 detail records)
  SUM                     0 0   0
  Hai Al-Salam CAP 1 1 Not Defined 20/12/12 20/12/12 PICD 100% DRC Not Defined 0 0   0
  Summary for Community: Hai Al-Salam (1 detail records)
  SUM                     0 0   0
  Kurdol CAP 1 1 Not Defined 23/12/12 23/12/12 PICD 100% DRC Not Defined 0 0   0
  Summary for Community: Kurdol (1 detail records)
  SUM                     0 0   0
Summary for District: Garsila (3 detail records)
SUM                     0 0   0
Grand Total (1,167 detail records)
SUM                     8,142,518 7,916,198   10,172,259
Page  First Previous Next Last  of 2
     Records 1 to 15 of 29      Groups per page 